3801 S BERRYMAN AVE 90066

Certificate Information: 3801 S BERRYMAN AVE 90066

Application / Permit
21010-10000-03959
Plan Check / Job No.
B21LA14463
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NFPA 13R FIRE SPRINKLERS REQUIRED. NEW 3-STORY ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PER SMALL LOT SUBDIVISION AA-2020-7920-PMLA 1 OF 2
Permit Issued
Issued on 8/11/2022
Issuing Office
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Issued 8/11/2022 APPLICANT
Building Plans Picked Up 8/11/2022 APPLICANT
CofO in Progress 7/11/2025 ARAM AVEDISIAN
Permit Finaled 7/18/2025 RICHARD STEINBACH
CofO Issued 7/18/2025 RICHARD STEINBACH
Permit Finaled 7/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/17/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/29/2021 ANTHONY MAINEZ
Sewer availability Cleared 11/29/2021 ANTHONY MAINEZ
Specific Plan Cleared 12/9/2021 VALERIA CEJA
Highway dedication Cleared 12/28/2021 RAYMOND MUGAMBWA
Trees in Parkway Cleared 12/29/2021 ADALBERTO VERA
Miscellaneous Cleared 4/22/2022 KENTON TRINH
Tract Map conditions Cleared 4/22/2022 KENTON TRINH
Low Impact Development Cleared 4/25/2022 SUNG JOON WON
Frnt yard landscape/Water mgmt Cleared 4/28/2022 KENTON TRINH
Building over 36-ft Cleared 8/11/2022 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 8/11/2022 JEANIE LAM

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/23/2023 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 5/31/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/31/2023 Approved JESUS RODRIGUEZ
Deputy Steel/Welding 6/15/2023 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 8/9/2023 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 9/25/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 9/25/2023 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/2/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 10/2/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/2/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/2/2023 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 10/2/2023 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 10/3/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/16/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 10/16/2023 Conditional Approval JESUS RODRIGUEZ
Gas Test 10/16/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 10/16/2023 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 10/16/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 10/16/2023 Conditional Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/16/2023 Conditional Approval JESUS RODRIGUEZ
Shower Pan 11/6/2023 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/9/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 11/9/2023 Approved JESUS RODRIGUEZ
Green Building Rough 11/9/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 11/9/2023 Approved JESUS RODRIGUEZ
Insulation 11/9/2023 Approved JESUS RODRIGUEZ
Insulation 11/9/2023 Off-Hour Fees Due
PLUMBING-Rough 11/9/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/9/2023 Approved JESUS RODRIGUEZ
Insulation 11/13/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 11/22/2023 Approved JESUS RODRIGUEZ
Sewer 2/22/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/15/2024 Approved JESUS RODRIGUEZ
Final 5/15/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 5/15/2024 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 5/15/2024 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 6/17/2024 Approved JESUS RODRIGUEZ
Gas Test 7/24/2024 Not Ready for Inspection JESUS RODRIGUEZ
Final 8/22/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 8/22/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Not Ready TEMISTOCLES CAAL
Smoke Detectors 8/22/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 9/18/2024 Corrections Issued JESUS PINEDA
Gas Test 9/18/2024 Corrections Issued JESUS PINEDA
Gas Test 9/26/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 9/26/2024 Corrections Issued JESUS PINEDA
Gas Test 10/23/2024 Approved JESUS PINEDA
PLUMBING-Final 10/23/2024 Approved JESUS PINEDA
Green Building Final 10/24/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Final 10/24/2024 Corrections Issued JESUS PINEDA
HVAC-Final 10/28/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/2/2025 Conditional Approval MICHAEL ALLEN
Final 6/2/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 6/2/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/2/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 6/4/2025 Not Ready for Inspection RUBEN RIVAS
Final 6/11/2025 Corrections Issued MICHAEL ALLEN
Special/Order Compliance 6/11/2025 Corrections Issued MICHAEL ALLEN
Final 7/9/2025 Not Ready for Inspection JESUS PINEDA
Final 7/11/2025 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 7/15/2025 Approved DAVID FEILER