408-410 E 101ST ST 90003

Certificate Information: 408-410 E 101ST ST 90003

Application / Permit
21010-10000-03946
Plan Check / Job No.
B21LA14400
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX WITH ATTACHED 1 CAR GARAGE AT FRONT AND 2 CAR GARAGE AT REAR.
Permit Issued
Issued on 9/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 DANIEL YIP
Corrections Issued 8/31/2021 DANIEL YIP
Quality Review Completed 9/3/2021 JASON HEALEY
Building Plans Picked Up 9/9/2021 APPLICANT
Plan Check Approved 6/30/2022 DANIEL YIP
Issued 9/6/2022 APPLICANT
CofO in Progress 4/3/2023 JAMES CHAVEZ
Permit Finaled 5/10/2023 DANIEL ORRANTE
CofO Issued 5/10/2023 DANIEL ORRANTE
Permit Finaled 5/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/22/2021 CELINA MORENO
Permit Cleared 9/22/2021 CELINA MORENO
Hydrant and Access approval Cleared 9/25/2021 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 10/13/2021 CELINA MORENO
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA
Sewer availability Cleared 10/22/2021 CELINA MORENO
Low Impact Development Cleared 6/20/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 6/23/2022 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2022 Approved JOHN KLARIN
Underground Mechanical 11/3/2022 Partial Approval JOHN KLARIN
Wood Frame 11/3/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Approval JOHN KLARIN
Insulation 11/4/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/12/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 1/12/2023 Approved JOHN KLARIN
Green Building Rough 1/12/2023 Approved JOHN KLARIN
HVAC-Rough 1/12/2023 Approved JOHN KLARIN
PLUMBING-Rough 1/12/2023 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 1/12/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 1/12/2023 Approved JOHN KLARIN
Insulation 1/13/2023 Approved JOHN KLARIN
Drywall Nailing 1/18/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 1/18/2023 Approved JOHN KLARIN
ELECTRICAL-Final 2/22/2023 Approved JOHN KLARIN
Service/Power Release 2/22/2023 Approved JOHN KLARIN
ELECTRICAL-Final 2/27/2023 No Access for Inspection JOHN KLARIN
ELECTRICAL-Final 3/1/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 3/15/2023 Not Ready for Inspection JAMES CHAVEZ
Final 3/15/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 3/15/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Final 3/15/2023 Approved JAMES CHAVEZ
PLUMBING-Final 3/15/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 3/15/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 3/16/2023 Approved JAMES CHAVEZ
Final 3/16/2023 OK to Issue CofO JAMES CHAVEZ
Green Building Final 3/16/2023 Approved JAMES CHAVEZ
PLUMBING-Final 3/16/2023 Approved JAMES CHAVEZ
Service/Power Release 3/16/2023 Approved JAMES CHAVEZ
Service/Power Release 3/20/2023 Approved JAMES CHAVEZ