225 N ST ANDREWS PL 90004

Certificate Information: 225 N ST ANDREWS PL 90004

Application / Permit
21010-10000-03941
Plan Check / Job No.
B21LA14389
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 3/21/2022
Issuing Office
Current Status
CofO Corrected on 8/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 CARLOS MONTES
Corrections Issued 8/31/2021 CARLOS MONTES
Quality Review Completed 9/2/2021 KEN GILL
Plan Check Approved 3/1/2022 CARLOS MONTES
Issued 3/21/2022 APPLICANT
Building Plans Picked Up 3/23/2022 APPLICANT
CofO in Progress 5/25/2023 JEFFREY MEAD
CofO Issued-Status Void 6/2/2023 DEROLD HAUFF
Permit Finaled-Status Void 6/2/2023 DEROLD HAUFF
Re-Activate Permit 8/31/2023 DEROLD HAUFF
Permit Finaled 8/31/2023 DEROLD HAUFF
CofO Corrected 8/31/2023 DEROLD HAUFF
Permit Finaled 8/31/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/29/2021 WALLIE JONG
Hydrant and Access approval Cleared 11/29/2021 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 12/27/2021 WALLIE JONG
Sewer availability Cleared 12/27/2021 WALLIE JONG
Low Impact Development Cleared 1/24/2022 TA ANH
Roof/Waste drainage to street Cleared 1/28/2022 WALLIE JONG

Contact Information

Contractor Snc Construction Inc; Lic. No.: 1079795-B 4032 WILSHIRE BL STE 410      LOS ANGELES, CA 90010
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2022 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 4/6/2022 Partial Approval STUART CHAPMAN
Underground Mechanical 4/6/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/13/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Conditional Approval SHAVONNE ESPINOZA
Deputy Wood Construction 4/27/2022 Conditional Approval SHAVONNE ESPINOZA
Deputy Wood Construction 5/5/2022 Conditional Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Corrections Issued SHAVONNE ESPINOZA
Wood Frame 5/6/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 6/22/2022 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 6/22/2022 Approved JEFFREY MEAD
PLUMBING-Rough 6/22/2022 Not Ready for Inspection JEFFREY MEAD
Underground Mechanical 6/22/2022 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 6/28/2022 Approved JEFFREY MEAD
PLUMBING-Rough 6/28/2022 Approved JEFFREY MEAD
Underground Mechanical 6/28/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 7/13/2022 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 7/13/2022 Approved JEFFREY MEAD
Insulation 7/20/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/20/2022 Partial Approval JEFFREY MEAD
Shower Pan 7/20/2022 Approved JEFFREY MEAD
Drywall Nailing 7/27/2022 Partial Approval JEFFREY MEAD
Green Building Rough 7/27/2022 Conditional Approval JEFFREY MEAD
Interior/Exterior Lathing 8/18/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 11/10/2022 Approved JEFFREY MEAD
Drywall Nailing 11/10/2022 Approved JEFFREY MEAD
Final 11/10/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Final 11/10/2022 Corrections Issued JEFFREY MEAD
Green Building Rough 11/10/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Not Ready JEFFREY MEAD
Service/Power Release 11/10/2022 Corrections Issued JEFFREY MEAD
Smoke Detectors 11/10/2022 Approved JEFFREY MEAD
Final 2/7/2023 Not Ready for Inspection JEFFREY MEAD
Green Building Final 2/7/2023 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved JEFFREY MEAD
Service/Power Release 2/7/2023 Not Ready for Inspection JEFFREY MEAD
Final 3/6/2023 Corrections Issued JEFFREY MEAD
Green Building Final 3/6/2023 Approved JEFFREY MEAD
Service/Power Release 3/6/2023 Not Required JEFFREY MEAD
ELECTRICAL-Final 5/24/2023 Approved JEFFREY MEAD
Final 5/24/2023 OK to Issue CofO JEFFREY MEAD
HVAC-Final 5/24/2023 Approved JEFFREY MEAD
PLUMBING-Final 5/24/2023 Approved JEFFREY MEAD
Service/Power Release 5/25/2023 Approved JEFFREY MEAD