225 N ST ANDREWS PL 90004
Certificate Information: 225 N ST ANDREWS PL 90004
- Application / Permit
- 21010-10000-03941
- Plan Check / Job No.
- B21LA14389
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 3/21/2022
- Issuing Office
- Current Status
- CofO Corrected on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | CARLOS MONTES |
| Corrections Issued | 8/31/2021 | CARLOS MONTES |
| Quality Review Completed | 9/2/2021 | KEN GILL |
| Plan Check Approved | 3/1/2022 | CARLOS MONTES |
| Issued | 3/21/2022 | APPLICANT |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| CofO in Progress | 5/25/2023 | JEFFREY MEAD |
| CofO Issued-Status Void | 6/2/2023 | DEROLD HAUFF |
| Permit Finaled-Status Void | 6/2/2023 | DEROLD HAUFF |
| Re-Activate Permit | 8/31/2023 | DEROLD HAUFF |
| Permit Finaled | 8/31/2023 | DEROLD HAUFF |
| CofO Corrected | 8/31/2023 | DEROLD HAUFF |
| Permit Finaled | 8/31/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/29/2021 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | WALLIE JONG |
| Sewer availability | Cleared | 12/27/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 1/24/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | WALLIE JONG |
Contact Information
| Contractor | Snc Construction Inc; Lic. No.: 1079795-B | 4032 WILSHIRE BL STE 410 LOS ANGELES, CA 90010 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/29/2022 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/6/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 4/6/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Deputy Wood Construction | 4/27/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Deputy Wood Construction | 5/5/2022 | Conditional Approval | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Wood Frame | 5/6/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 6/22/2022 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 6/22/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 6/22/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 6/22/2022 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/28/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 6/28/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 6/28/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/13/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 7/13/2022 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 7/13/2022 | Approved | JEFFREY MEAD |
| Insulation | 7/20/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/20/2022 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 7/20/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 7/27/2022 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 7/27/2022 | Conditional Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/18/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/10/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/10/2022 | Approved | JEFFREY MEAD |
| Final | 11/10/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 11/10/2022 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 11/10/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Service/Power Release | 11/10/2022 | Corrections Issued | JEFFREY MEAD |
| Smoke Detectors | 11/10/2022 | Approved | JEFFREY MEAD |
| Final | 2/7/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 2/7/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 3/6/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/6/2023 | Approved | JEFFREY MEAD |
| Service/Power Release | 3/6/2023 | Not Required | JEFFREY MEAD |
| ELECTRICAL-Final | 5/24/2023 | Approved | JEFFREY MEAD |
| Final | 5/24/2023 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 5/24/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/24/2023 | Approved | JEFFREY MEAD |
| Service/Power Release | 5/25/2023 | Approved | JEFFREY MEAD |