4020 W AVENUE 41 90065
Certificate Information: 4020 W AVENUE 41 90065
- Application / Permit
- 21010-10000-03931
- Plan Check / Job No.
- B21LA14319
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert 1st floor garage into ADU per State law
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/4/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/13/2021 | HERNAN ARREOLA |
| Plan Check Approved | 8/30/2021 | HERNAN ARREOLA |
| Issued | 9/8/2021 | APPLICANT |
| CofO in Progress | 5/2/2023 | BRIAN SULLIVAN |
| No Progress | 9/27/2023 | SCOTT FINNILA |
| CofO in Progress | 12/1/2023 | SCOTT FINNILA |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/14/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | CECILIO NAVARRO |
| Supp. Use District POD/CDO/TDO | Cleared | 8/26/2021 | ADRINEH MELKONIAN |
| GPI Written Notices | Cleared | 8/30/2021 | HERNAN ARREOLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/14/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/23/2022 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/29/2022 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 12/29/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/13/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 1/13/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 1/24/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 1/24/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 2/17/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/17/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 2/23/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 2/23/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 2/23/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/31/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/31/2023 | Corrections Issued | CRAIG VAUGHAN |
| Final | 3/31/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 3/31/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 3/31/2023 | Approved | CRAIG VAUGHAN |
| MERV13>=Final | 3/31/2023 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 3/31/2023 | Approved | CRAIG VAUGHAN |
| METHANE-Final | 3/31/2023 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 3/31/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/31/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/31/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/1/2023 | Approved | BRIAN SULLIVAN |
| Final | 5/1/2023 | OK to Issue CofO | BRIAN SULLIVAN |
| HVAC-Final | 5/1/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 5/1/2023 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 10/13/2023 | Corrections Issued | SCOTT FINNILA |