3221 E 2ND ST 90063

Certificate Information: 3221 E 2ND ST 90063

Application / Permit
21010-10000-03925
Plan Check / Job No.
B21LA14275
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 30'x30' ONE STORY ACCESSORY DWELLING UNIT(1,200 SF max per Ordinanc, LAMC 12.22 A.33 (c)-(d)); ALL CONSTRUCTION PER WFPP
Permit Issued
Issued on 1/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/6/2021 SINA KHOSRAVI
Corrections Issued 8/8/2021 SINA KHOSRAVI
Applicant returned to address corrections 2/16/2022 SHANGQIN XIE
Building Plans Picked Up 2/22/2022 APPLICANT
Plan Check Approved 6/2/2022 ZAW HAN
Plan Check Approved 6/2/2022 AUNG SOE
Issued 1/19/2023 APPLICANT
CofO in Progress 11/27/2024 FREDDIE RIVERA
Permit Finaled 11/30/2024 DEROLD HAUFF
CofO Issued 11/30/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 9/3/2021 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 9/9/2021 JEANIE LAM
Sewer availability Cleared 9/9/2021 JEANIE LAM
Grading Pre-Inspection Cleared 9/14/2021 VASIL MIHALEV
Address approval Cleared 10/15/2021 CHRISTOPHER ROCHA
Low Impact Development Cleared 12/15/2021 TA ANH
Roof/Waste drainage to street Cleared 1/13/2022 ABEL CASILLAS
GPI Written Notices Cleared 1/25/2022 FELIX FIGUEROA

Contact Information

Contractor Polymath Development Group Inc; Lic. No.: 1069728-B 616 ST PAUL AVE APT 503      LOS ANGELES, CA 90017
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2023 Partial Approval ALIZAH MAYAGOITIA
Sewer 3/30/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 3/30/2023 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 4/6/2023 Corrections Issued FREDDIE RIVERA
Underground Mechanical 4/19/2023 Partial Approval FREDDIE RIVERA
Deputy Methane Barrier 4/26/2023 Conditional Approval FREDDIE RIVERA
METHANE-Barrier 5/3/2023 Approved FREDDIE RIVERA
Special/Order Compliance 5/9/2023 Corrections Issued FREDDIE RIVERA
Deputy Methane Barrier 5/16/2023 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 5/18/2023 Approved FREDDIE RIVERA
METHANE-Subgrade 5/18/2023 Approved FREDDIE RIVERA
Deputy Methane Barrier 5/19/2023 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 6/20/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 6/20/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Conditional Approval FREDDIE RIVERA
Green Building Rough 6/20/2023 Partial Inspection FREDDIE RIVERA
HVAC-Rough 6/20/2023 Corrections Issued FREDDIE RIVERA
METHANE-Rough 6/20/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 6/20/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 6/20/2023 Partial Inspection FREDDIE RIVERA
Wood Frame 6/20/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 8/1/2023 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Conditional Approval FREDDIE RIVERA
Green Building Rough 8/1/2023 Approved FREDDIE RIVERA
HVAC-Rough 8/1/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 8/1/2023 Approved FREDDIE RIVERA
Wood Frame 8/1/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/21/2023 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 8/28/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Approved FREDDIE RIVERA
HVAC-Rough 8/28/2023 Approved FREDDIE RIVERA
Insulation 8/30/2023 Corrections Issued FREDDIE RIVERA
Drywall Nailing 9/7/2023 Approved FREDDIE RIVERA
Shower Pan 9/7/2023 Approved FREDDIE RIVERA
Insulation 9/12/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/12/2023 Approved FREDDIE RIVERA
ELECTRICAL-Final 10/11/2024 Corrections Issued FREDDIE RIVERA
Final 10/11/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 10/11/2024 Corrections Issued FREDDIE RIVERA
HVAC-Final 10/11/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 10/11/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Approved FREDDIE RIVERA
Service/Power Release 10/11/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 10/11/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 10/21/2024 Partial Inspection FREDDIE RIVERA
Final 10/21/2024 Partial Inspection FREDDIE RIVERA
Gas Test 10/21/2024 Approved FREDDIE RIVERA
Green Building Final 10/21/2024 Conditional Approval FREDDIE RIVERA
HVAC-Final 10/21/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 10/21/2024 Approved FREDDIE RIVERA
Service/Power Release 10/21/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 10/24/2024 Approved FREDDIE RIVERA
Final 10/24/2024 OK to Issue CofO FREDDIE RIVERA
Green Building Final 10/24/2024 Approved FREDDIE RIVERA
HVAC-Final 10/24/2024 Approved FREDDIE RIVERA
Service/Power Release 10/24/2024 Approved FREDDIE RIVERA