463 S ARDMORE AVE 90004

Certificate Information: 463 S ARDMORE AVE 90004

Application / Permit
21010-10000-03914
Plan Check / Job No.
B21LA14257
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 18' x 22' detached garage to ADU
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 6/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/3/2021 JOE VO
Corrections Issued 8/3/2021 JOE VO
Plan Check Approved 8/26/2021 JOE VO
Issued 9/8/2021 APPLICANT
CofO in Progress 5/30/2023 JEFFREY MEAD
Permit Finaled 6/1/2023 RONALD MYRICK
CofO Issued 6/1/2023 RONALD MYRICK
Permit Finaled 6/1/2023 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 8/9/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/11/2021 CECILIO NAVARRO
Address approval Cleared 8/18/2021 THOMAS LANG

Contact Information

Contractor M L Builders And Design; Lic. No.: 953612-B 10400 GLORIA AVENUE      GRANADA HILLS, CA 91344

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/15/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 12/20/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 12/20/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 12/20/2021 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 1/11/2022 Approved JOSEPH MCGARRY
HVAC-Rough 1/11/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/11/2022 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 2/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Shower Pan 2/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Final 11/23/2022 Partial Approval JEFFREY MEAD
Green Building Final 11/23/2022 Partial Approval JEFFREY MEAD
HVAC-Final 11/23/2022 Partial Approval JEFFREY MEAD
PLUMBING-Final 11/23/2022 Approved JEFFREY MEAD
Service/Power Release 11/23/2022 Not Required JEFFREY MEAD
Smoke Detectors 11/23/2022 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 2/24/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Final 2/24/2023 Approved JOSEPH MCGARRY
Final 2/24/2023 Corrections Issued JOSEPH MCGARRY
Green Building Final 2/24/2023 Approved JOSEPH MCGARRY
Green Building Rough 2/24/2023 Approved JOSEPH MCGARRY
HVAC-Final 2/24/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 2/24/2023 Approved JOSEPH MCGARRY
Final 3/14/2023 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved JEFFREY MEAD
Final 5/22/2023 Corrections Issued JEFFREY MEAD
Final 5/30/2023 OK to Issue CofO JEFFREY MEAD