1019-1019 1/4 E 84TH PL 90001

Certificate Information: 1019-1019 1/4 E 84TH PL 90001

Application / Permit
21010-10000-03910
Plan Check / Job No.
B21LA14254
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSE 2-STORY (62' X 34.5') DUPLEX (ZC: 3720 SF) AT FRONT. 1 OF 2
Permit Issued
Issued on 3/7/2022
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 VIVIAN LAO
Corrections Issued 9/2/2021 VIVIAN LAO
Quality Review Completed 9/14/2021 MICHAEL PEREZ
Applicant returned to address corrections 2/7/2022 VIVIAN LAO
Plan Check Approved 2/11/2022 VIVIAN LAO
Issued 3/7/2022 APPLICANT
Building Plans Picked Up 3/9/2022 APPLICANT
CofO in Progress 8/31/2023 MICHAEL LEWIS
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/30/2021 WALLIE JONG
Permit Cleared 9/30/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/4/2021 WALLIE JONG
Sewer availability Cleared 10/18/2021 WALLIE JONG
Low Impact Development Cleared 12/2/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 12/2/2021 WALLIE JONG
Hydrant and Access approval Cleared 1/19/2022 GREGORY HOERNER

Contact Information

Contractor Moreno Chris; Lic. No.: 973501-B 1158 W 126TH STREET      LOS ANGELES, CA 90044
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/6/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 4/20/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 7/11/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 7/11/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 7/12/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 7/12/2022 Approved LILIANA PORTILLO
Green Building Rough 7/12/2022 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 7/12/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/19/2022 Approved LILIANA PORTILLO
Green Building Rough 7/19/2022 Approved LILIANA PORTILLO
Insulation 7/19/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 8/4/2022 Conditional Approval LILIANA PORTILLO
Interior/Exterior Lathing 8/4/2022 Partial Approval LILIANA PORTILLO
Sewer 8/31/2022 Approved LILIANA PORTILLO
Underground Mechanical 8/31/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/31/2023 Partial Approval MICHAEL LEWIS
Drywall Nailing 8/4/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 8/4/2023 Approved MICHAEL LEWIS
Final 8/4/2023 Conditional Approval MICHAEL LEWIS
Green Building Final 8/4/2023 Approved MICHAEL LEWIS
HVAC-Final 8/4/2023 Approved MICHAEL LEWIS
PLUMBING-Final 8/4/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 8/4/2023 Approved MICHAEL LEWIS
Smoke Detectors 8/4/2023 Approved MICHAEL LEWIS
Final 8/30/2023 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 8/30/2023 Approved MICHAEL LEWIS