912 W 65TH ST 90044

Certificate Information: 912 W 65TH ST 90044

Application / Permit
21010-10000-03902
Plan Check / Job No.
B21LA14247
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE (FRONT BUILDING).
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 ERWIN PASCUA
Corrections Issued 8/31/2021 ERWIN PASCUA
Quality Review Completed 8/31/2021 SAI KHUM
Applicant returned to address corrections 12/17/2021 ERWIN PASCUA
Applicant returned to address corrections 12/21/2021 ERWIN PASCUA
Applicant returned to address corrections 12/22/2021 ERWIN PASCUA
Plan Check Approved 12/30/2021 ERWIN PASCUA
Issued 2/18/2022 APPLICANT
Building Plans Picked Up 2/23/2022 APPLICANT
CofO in Progress 10/18/2022 LILIANA PORTILLO
Permit Finaled 10/28/2022 DEROLD HAUFF
CofO Issued 10/28/2022 DEROLD HAUFF
Permit Finaled 10/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 9/14/2021 DANIEL CORONADO
Address approval Cleared 9/15/2021 WALLIE JONG
Permit Cleared 9/15/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/21/2021 WALLIE JONG
Sewer availability Cleared 9/24/2021 WALLIE JONG
Low Impact Development Cleared 10/18/2021 TA ANH
Roof/Waste drainage to street Cleared 10/21/2021 CELINA MORENO
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 11/19/2021 GILBERT URREA
Green Code Cleared 12/21/2021 ERWIN PASCUA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/25/2022 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/25/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Approved LILIANA PORTILLO
HVAC-Rough 5/31/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 5/31/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/1/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 6/1/2022 Approved LILIANA PORTILLO
Green Building Rough 6/1/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 6/1/2022 Approved LILIANA PORTILLO
Insulation 6/6/2022 Approved LILIANA PORTILLO
Underground Mechanical 6/14/2022 Approved LILIANA PORTILLO
Drywall Nailing 6/27/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/27/2022 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 6/30/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/16/2022 Partial Approval LILIANA PORTILLO
ELECTRICAL-Final 10/12/2022 Approved LILIANA PORTILLO
Final 10/12/2022 OK to Issue CofO LILIANA PORTILLO
Green Building Final 10/12/2022 Approved LILIANA PORTILLO
HVAC-Final 10/12/2022 Approved LILIANA PORTILLO
PLUMBING-Final 10/12/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/12/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 10/12/2022 Approved LILIANA PORTILLO
Smoke Detectors 10/12/2022 Approved LILIANA PORTILLO
Service/Power Release 10/14/2022 Approved LILIANA PORTILLO