1117 1/2 N LANARK ST 90041

Certificate Information: 1117 1/2 N LANARK ST 90041

Application / Permit
21010-10000-03895
Plan Check / Job No.
B21LA14216
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan Check* PROPOSED 1 STORY ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 10/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 CRYSTEL MAALOUF
Corrections Issued 9/10/2021 CRYSTEL MAALOUF
Quality Review Completed 9/21/2021 WING SUEN
Applicant returned to address corrections 12/9/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 12/16/2021 CRYSTEL MAALOUF
Plan Check Approved 1/28/2022 CRYSTEL MAALOUF
Issued 3/18/2022 APPLICANT
CofO in Progress 10/19/2022 CRAIG VAUGHAN
CofO in Progress 10/25/2022 CRAIG VAUGHAN
Permit Finaled 10/26/2022 DEROLD HAUFF
Permit Finaled 10/26/2022 DEROLD HAUFF
CofO Issued 10/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/25/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 11/16/2021 PAMELA TENEZA
Sewer availability Cleared 11/16/2021 PAMELA TENEZA
Grading Pre-Inspection Cleared 12/1/2021 PATRICK MISCHLICH
GPI Written Notices Cleared 12/16/2021 CRYSTEL MAALOUF
Hydrant and Access approval Cleared 12/18/2021 JOHN CONNEALLY
Low Impact Development Cleared 1/13/2022 KHAING AYE
Roof/Waste drainage to street Cleared 1/20/2022 WALLIE JONG

Contact Information

Contractor Reyes Luis Construction Inc; Lic. No.: 986151-B 9424 LOCH LOMOND DRIVE      PICO RIVERA, CA 90660
Engineer Graciano,, Daniel Banuelos; Lic. No.: C57297 1340 N MURRAY ST      BANNING, CA 92220

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2022 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 4/11/2022 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/18/2022 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/21/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/11/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Partial Approval CRAIG VAUGHAN
Gas Test 5/11/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/11/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/17/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/17/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/17/2022 Approved CRAIG VAUGHAN
Shower Pan 5/17/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/17/2022 Approved CRAIG VAUGHAN
Insulation 5/19/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/19/2022 Approved CRAIG VAUGHAN
Drywall Nailing 5/24/2022 Approved RUBEN SALAS
Gas Test 7/27/2022 Approved CRAIG VAUGHAN
Sewer 7/27/2022 Approved CRAIG VAUGHAN
Final 9/27/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 9/27/2022 Approved CRAIG VAUGHAN
Green Building Final 9/27/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 9/27/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 9/27/2022 Approved CRAIG VAUGHAN
Final 10/12/2022 Corrections Issued CRAIG VAUGHAN
Service/Power Release 10/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 10/18/2022 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 10/18/2022 Approved CRAIG VAUGHAN
Final 10/21/2022 OK to Issue CofO CRAIG VAUGHAN