3041 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3041 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21010-10000-03853
- Plan Check / Job No.
- B21LA14080
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 12/23/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | DANIEL YIP |
| Corrections Issued | 8/24/2021 | DANIEL YIP |
| Quality Review Completed | 8/31/2021 | JASON HEALEY |
| Applicant returned to address corrections | 10/19/2021 | DANIEL YIP |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Plan Check Approved | 12/15/2021 | DANIEL YIP |
| Issued | 12/23/2021 | APPLICANT |
| CofO in Progress | 4/23/2024 | JESUS PINEDA |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
| CofO Issued | 5/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | DINAH GARIN |
| Permit | Cleared | 9/9/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | DINAH GARIN |
| Sewer availability | Cleared | 9/21/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 10/19/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 10/19/2021 | DANIEL YIP |
| Low Impact Development | Cleared | 11/3/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/5/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 11/10/2021 | TINA MIRANDA |
| Trees in Parkway | Cleared | 11/18/2021 | ADALBERTO VERA |
| Specific Plan | Cleared | 11/30/2021 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Gruenbaum,, Nathan Henry; Lic. No.: C22262 | 6337 LINDENHURST AVENUE LOS ANGELES, CA 90048 |
| Engineer | Khanlou,, Amir; Lic. No.: C87550 | 10671 HOLMAN AVE APT 207 LOS ANGELES, CA 90024 |
| Engineer | Toufighi,, Pejman; Lic. No.: M31480 | 3807 DAGURRE AVE CALABASAS, CA 91302 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2022 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 3/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 3/16/2022 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 3/23/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Steel/Welding | 3/24/2022 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 4/13/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 4/25/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 5/13/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 6/13/2022 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 6/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 6/29/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 6/29/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/25/2022 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/22/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 8/22/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/22/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/22/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Inspection | 9/26/2022 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/11/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 10/11/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 10/13/2022 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 10/17/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/1/2022 | No Access for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 11/10/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 2/6/2023 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/14/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 2/14/2023 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 3/9/2023 | Partial Approval | DAVID FEILER |
| Sewer | 3/29/2023 | Approved | JOHNNY MIRANDA |
| Enclosure/Fence | 5/17/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 8/7/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/17/2023 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 10/16/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 10/16/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 4/18/2024 | Approved | JESUS PINEDA |
| Final | 4/18/2024 | Corrections Issued | JESUS PINEDA |
| Gas Test | 4/18/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 4/18/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/18/2024 | Approved | JESUS PINEDA |
| Service/Power Release | 4/18/2024 | Not Ready for Inspection | JESUS PINEDA |
| Final | 4/23/2024 | OK to Issue CofO | JESUS PINEDA |
| Footing/Foundation/Slab | 4/23/2024 | Approved | JESUS PINEDA |
| Green Building Final | 4/23/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 4/23/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 4/23/2024 | Approved | JESUS PINEDA |