2114 S HILLCREST DR 90016
Certificate Information: 2114 S HILLCREST DR 90016
- Application / Permit
- 21010-10000-03850
- Plan Check / Job No.
- B21LA14067
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 1-STORY ADDITION AND CONVERSION OF EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 12/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | MICHAEL LOPEZ |
| Corrections Issued | 7/30/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/4/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/26/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 12/1/2021 | MICHAEL LOPEZ |
| Issued | 12/7/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | WILLIAM MICHALAK |
| CofO Issued | 12/16/2022 | DANIEL SANCHEZ |
| Permit Finaled | 12/16/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| CPC | Cleared | 8/6/2021 | RICHARD REASER |
| Address approval | Cleared | 8/9/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/13/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/3/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 10/25/2021 | CHRIS PARK |
| Roof/Waste drainage to street | Cleared | 11/19/2021 | AMAAN MALIK |
Contact Information
| No Data Available. |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/14/2022 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 1/18/2022 | Corrections Issued | GLEN RAND |
| Footing/Foundation/Slab | 1/20/2022 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 1/26/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 3/7/2022 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 3/7/2022 | Approved | WILLIAM MICHALAK |
| MERV13>=Rough | 3/7/2022 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 3/15/2022 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 3/15/2022 | Partial Approval | WILLIAM MICHALAK |
| Insulation | 3/22/2022 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 3/22/2022 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 4/4/2022 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/22/2022 | Approved | WILLIAM MICHALAK |
| Final | 7/22/2022 | OK to Issue CofO | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 7/22/2022 | Approved | WILLIAM MICHALAK |
| Green Building Final | 7/22/2022 | Approved | WILLIAM MICHALAK |
| MERV13>=Final | 7/22/2022 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 7/22/2022 | Approved | WILLIAM MICHALAK |