10872 W DORA ST 91352

Certificate Information: 10872 W DORA ST 91352

Application / Permit
21010-10000-03839
Plan Check / Job No.
B21LA14046
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1 STORY SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 STARR CHEN
Corrections Issued 9/5/2021 STARR CHEN
Quality Review Completed 9/9/2021 JASON HEALEY
Building Plans Picked Up 9/14/2021 APPLICANT
Plan Check Approved 2/3/2022 STARR CHEN
Issued 2/14/2022 APPLICANT
CofO in Progress 8/24/2022 DAVID ANDERSON
Permit Finaled 9/29/2022 MICHAEL SMITH
CofO Issued 9/29/2022 MICHAEL SMITH
Permit Finaled 9/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/13/2021 CARLOS AGUILERA
Sewer availability Cleared 10/13/2021 CARLOS AGUILERA
Low Impact Development Cleared 12/20/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/27/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/10/2022 KURT CORRAL
Clean Up Green Up Cleared 1/13/2022 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 2/28/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Pre-Inspection 2/28/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 2/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/8/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 3/8/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/8/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Approved CHRISTOPHER DELLEFIELD
Gas Test 4/13/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/13/2022 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 4/21/2022 Partial Approval CHRISTOPHER DELLEFIELD
Gas Test 4/27/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/27/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/27/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/3/2022 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 5/3/2022 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 5/3/2022 Approved MATTHEW NELSON
Wood Frame 5/3/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 5/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 5/13/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 5/13/2022 Approved WILLIAM WREN
Drywall Nailing 5/18/2022 Approved THOMAS FINNILA
Service/Power Release 6/21/2022 Not Ready for Inspection DAVID ANDERSON
Sewer 6/21/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 6/24/2022 Approved DAVID ANDERSON
Service/Power Release 6/24/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 7/15/2022 Approved DAVID ANDERSON
Final 7/15/2022 Not Ready for Inspection DAVID ANDERSON
Green Building Final 7/15/2022 Approved DAVID ANDERSON
Green Building Rough 7/15/2022 Approved DAVID ANDERSON
HVAC-Final 7/15/2022 Approved DAVID ANDERSON
PLUMBING-Final 7/15/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Approved DAVID ANDERSON
Smoke Detectors 7/15/2022 Approved DAVID ANDERSON
Final 7/28/2022 Corrections Issued DAVID ANDERSON
Gas Test 7/28/2022 Approved DAVID ANDERSON
Final 8/24/2022 OK to Issue CofO DAVID ANDERSON