1175 E 41ST PL 90011
Certificate Information: 1175 E 41ST PL 90011
- Application / Permit
- 21010-10000-03836
- Plan Check / Job No.
- B21LA14038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- new 2 car garage
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 9/21/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/29/2021 | KEN GILL |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Plan Check Approved | 3/3/2022 | ARSALAN SHABESTARI |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 1/11/2023 | BRENDAN MORELLI |
| CofO Issued | 1/27/2023 | DEROLD HAUFF |
| Permit Finaled | 1/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 10/20/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 10/20/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 12/9/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/3/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/9/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 4/15/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/24/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/16/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/22/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 7/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 7/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 7/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 7/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 7/21/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/21/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 7/21/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Gas Test | 8/2/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 8/2/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | JULIAN AMAYA |
| Final | 12/1/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Green Building Final | 12/1/2022 | Not Ready for Inspection | JULIAN AMAYA |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Not Ready | JULIAN AMAYA |
| Service/Power Release | 12/1/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Smoke Detectors | 12/1/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Final | 12/9/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Green Building Final | 12/9/2022 | Approved | JULIAN AMAYA |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | JULIAN AMAYA |
| Service/Power Release | 12/9/2022 | Not Required | JULIAN AMAYA |
| Smoke Detectors | 12/9/2022 | Approved | JULIAN AMAYA |
| Final | 12/19/2022 | Partial Inspection | BRENDAN MORELLI |
| Final | 12/27/2022 | OK to Issue CofO | BRENDAN MORELLI |