1175 E 41ST PL 90011

Certificate Information: 1175 E 41ST PL 90011

Application / Permit
21010-10000-03836
Plan Check / Job No.
B21LA14038
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
new 2 car garage
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
CofO Issued on 1/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 ARSALAN SHABESTARI
Corrections Issued 9/21/2021 ARSALAN SHABESTARI
Quality Review Completed 9/29/2021 KEN GILL
Building Plans Picked Up 11/12/2021 APPLICANT
Plan Check Approved 3/3/2022 ARSALAN SHABESTARI
Issued 3/3/2022 APPLICANT
CofO in Progress 1/11/2023 BRENDAN MORELLI
CofO Issued 1/27/2023 DEROLD HAUFF
Permit Finaled 1/27/2023 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 10/20/2021 DENZEL HENDERSON
ZA Case Cleared 10/20/2021 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 11/1/2021 STEVE MELGAR
Hydrant and Access approval Cleared 12/9/2021 MATTHEW CRAIG
Low Impact Development Cleared 2/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/9/2022 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/17/2022 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 4/15/2022 No Access for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 4/22/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 5/19/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/24/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 6/16/2022 Conditional Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/22/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Approved JOAQUIN GREENOUGH
Gas Test 7/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 7/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 7/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 7/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Gas Test 7/21/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 7/21/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 7/21/2022 Partial Approval JOAQUIN GREENOUGH
Wood Frame 7/21/2022 Corrections Issued JOAQUIN GREENOUGH
Gas Test 8/2/2022 Approved JOAQUIN GREENOUGH
Wood Frame 8/2/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/1/2022 Approved JULIAN AMAYA
Final 12/1/2022 Not Ready for Inspection JULIAN AMAYA
Green Building Final 12/1/2022 Not Ready for Inspection JULIAN AMAYA
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Not Ready JULIAN AMAYA
Service/Power Release 12/1/2022 Not Ready for Inspection JULIAN AMAYA
Smoke Detectors 12/1/2022 Not Ready for Inspection JULIAN AMAYA
Final 12/9/2022 Not Ready for Inspection JULIAN AMAYA
Green Building Final 12/9/2022 Approved JULIAN AMAYA
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Approved JULIAN AMAYA
Service/Power Release 12/9/2022 Not Required JULIAN AMAYA
Smoke Detectors 12/9/2022 Approved JULIAN AMAYA
Final 12/19/2022 Partial Inspection BRENDAN MORELLI
Final 12/27/2022 OK to Issue CofO BRENDAN MORELLI