503 E 21ST ST 90011
Certificate Information: 503 E 21ST ST 90011
- Application / Permit
- 21010-10000-03829
- Plan Check / Job No.
- B21LA14015
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING (FRONT BUILDING). 1 OF 2
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 12/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 8/23/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 8/25/2021 | KEN GILL |
| Applicant returned to address corrections | 12/22/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/19/2022 | CRYSTEL MAALOUF |
| Issued | 4/1/2022 | APPLICANT |
| Building Plans Picked Up | 4/5/2022 | APPLICANT |
| CofO in Progress | 11/18/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/6/2022 | DEROLD HAUFF |
| CofO Issued | 12/6/2022 | DEROLD HAUFF |
| Permit Finaled | 12/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 9/14/2021 | DANIEL CORONADO |
| Address approval | Cleared | 9/15/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/19/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 12/9/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CELINA MORENO |
| Sewer availability | Cleared | 1/14/2022 | WALLIE JONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 5/23/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 5/23/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 5/24/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/25/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/25/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 8/11/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/26/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/26/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 9/26/2022 | Approved | RYAN SALAZAR |
| Underground Mechanical | 9/26/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 10/20/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/17/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/17/2022 | Approved | ALEJANDRO DE ARTOLA |