1771-1831 W BLAKE AVE 90031

Certificate Information: 1771-1831 W BLAKE AVE 90031

Application / Permit
21010-10000-03776
Plan Check / Job No.
B21LA13961
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CAR GARAGE (BLDG 60). 60 OF 100
Permit Issued
Issued on 7/28/2023
Issuing Office
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 FARSHAD ALIMOHAMADI
Corrections Issued 11/18/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 11/23/2021 SAI KHUM
Building Plans Picked Up 11/23/2021 APPLICANT
Applicant returned to address corrections 2/3/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/15/2022 FARSHAD ALIMOHAMADI
Disabled Access Plans Picked Up 3/10/2022 APPLICANT
Green Plans Picked Up 3/16/2022 APPLICANT
Applicant returned to address corrections 3/18/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/21/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/30/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/19/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/26/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/21/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/22/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/3/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/17/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/18/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/20/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/13/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/15/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/16/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/20/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 7/17/2023 FARSHAD ALIMOHAMADI
Issued 7/28/2023 APPLICANT
CofO in Progress 10/15/2025 BRENDAN MORELLI
Permit Finaled 10/17/2025 DEROLD HAUFF
CofO Issued 10/17/2025 DEROLD HAUFF
Permit Finaled 10/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Highway dedication Cleared 2/16/2022 JEANIE LAM
Permit Cleared 2/17/2022 MATIAS FARFAN
Eng Process Fee Ord 176,300 Cleared 2/24/2022 STEVE MELGAR
Sewer availability Cleared 4/13/2022 JEANIE LAM
Address approval Cleared 4/26/2022 JEANETTE VONG
Driveway location Cleared 5/10/2022 PETE EYRE
Internal circulation Cleared 5/10/2022 PETE EYRE
Construction near power lines Cleared 8/11/2022 WALTER RAMIREZ
"Q" conditions Cleared 8/24/2022 DANIEL CORONADO
Miscellaneous Cleared 8/24/2022 DANIEL CORONADO
Miscellaneous Cleared 8/24/2022 DANIEL CORONADO
Opn space landscape/Water mgmt Cleared 8/24/2022 DANIEL CORONADO
Prkng lot landscape/Water mgmt Cleared 8/24/2022 DANIEL CORONADO
Site Plan review Cleared 8/24/2022 DANIEL CORONADO
Tract Map conditions Cleared 8/24/2022 DANIEL CORONADO
Tract Map conditions Cleared 8/24/2022 DANIEL CORONADO
ZI Cleared 8/24/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 9/2/2022 JOHN CONNEALLY
Low Impact Development Cleared 1/26/2023 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/30/2023 TERRY PHAN
Building over 36-ft Cleared 7/17/2023 CALOSHA APPROVED

Contact Information

Architect Cunningham,, Gary Lynn; Lic. No.: C29285 18162 LILLIAN WAY      TUSTIN, CA 92780
Contractor Hillcrest Construction Group Llc; Lic. No.: 1086392-B 1875 CENTURY PARK EAST   SUITE 1130    LOS ANGELES, CA 90067
Engineer Burica,, Michael Jerome; Lic. No.: C57151 9283 RESEARCH DR      IRVINE, CA 92618

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/30/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/4/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 11/7/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 1/10/2024 Conditional Approval BRENDAN MORELLI
Drywall Nailing 1/18/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 3/4/2024 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval SCOTT FINNILA
Drywall Nailing 3/15/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval BRENDAN MORELLI
Drywall Nailing 4/22/2024 Partial Approval BRENDAN MORELLI
Drywall Nailing 5/10/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 7/3/2024 Partial Approval SCOTT FINNILA
PLUMBING-Rough 8/6/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 8/26/2024 Not Ready for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 8/28/2024 Partial Approval BRENDAN MORELLI
HVAC-Rough 8/29/2024 Approved BRENDAN MORELLI
ELECTRICAL-Rough 9/3/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 9/19/2024 Approved BRENDAN MORELLI
Green Building Rough 9/19/2024 Approved BRENDAN MORELLI
MERV13>=Rough 9/19/2024 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 9/19/2024 Approved BRENDAN MORELLI
Insulation 9/23/2024 Not Ready for Inspection BRENDAN MORELLI
Insulation 9/25/2024 Approved BRENDAN MORELLI
Drywall Nailing 10/1/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 12/5/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 3/6/2025 Approved BRENDAN MORELLI
HVAC-Final 3/6/2025 Partial Approval BRENDAN MORELLI
PLUMBING-Final 3/24/2025 Approved BRENDAN MORELLI
Pre-Inspection 4/4/2025 Approved BRENDAN MORELLI
Service/Power Release 6/23/2025 Approved BRENDAN MORELLI
Final 10/10/2025 OK to Issue CofO BRENDAN MORELLI
Footing/Foundation/Slab 10/10/2025 Approved BRENDAN MORELLI
Green Building Final 10/10/2025 Approved BRENDAN MORELLI
MERV13>=Final 10/10/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV No Gas BRENDAN MORELLI
Smoke Detectors 10/10/2025 Approved BRENDAN MORELLI