15418 W BERMUDA ST 91345

Certificate Information: 15418 W BERMUDA ST 91345

Application / Permit
21010-10000-03679
Plan Check / Job No.
B21LA13829
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 52-unit, 4-story affordable housing apartment building with 3 levels type IIIA over 1 level type IA. 4 very low income units and 3 extremely low income units per CPC-2017-627-VZCJ-SPR
Permit Issued
Issued on 9/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 KEVIN MORALES
Corrections Issued 9/10/2021 KEVIN MORALES
Quality Review Completed 9/14/2021 EUGENE BARBEAU
Building Plans Picked Up 9/22/2021 APPLICANT
Disabled Access Plans Picked Up 10/6/2021 APPLICANT
Applicant returned to address corrections 1/11/2022 KEVIN MORALES
Applicant returned to address corrections 1/20/2022 KEVIN MORALES
Applicant returned to address corrections 8/9/2022 KEVIN MORALES
Plan Check Approved 9/2/2022 KEVIN MORALES
Issued 9/23/2022 APPLICANT
TCO Issued (Expire Date: 12-29-2025) 7/2/2025 RICKEY JACKSON
CofO in Progress 10/1/2025 ROBERT DAVIS
Permit Finaled 10/7/2025 RICKEY JACKSON
CofO Issued 10/7/2025 RICKEY JACKSON
Permit Finaled 10/7/2025 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 10/12/2021 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 11/1/2021 CARLOS AGUILERA
Green Code Cleared 1/7/2022 KEVIN MORALES
Trees in Parkway Cleared 2/2/2022 ADALBERTO VERA
Tract Map conditions Cleared 2/3/2022 LOUIS ORTEGA
Tract Map conditions Cleared 2/3/2022 LOUIS ORTEGA
Tract Map conditions Cleared 2/3/2022 LOUIS ORTEGA
ZA Case Cleared 2/3/2022 LOUIS ORTEGA
Hydrant and Access approval Cleared 4/4/2022 KURT CORRAL
DCP conditions approval Cleared 4/6/2022 RICHARD TRUONG
Fire Marshal Fire Life Safety Cleared 4/18/2022 ANDREW KO
DAS Clearance Cleared 5/18/2022 KEVIN MORALES
Low Impact Development Cleared 6/2/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/2/2022 DAGOVERTO GUERRERO
Highway dedication Cleared 6/23/2022 LEE GUILBEAUX
Permit Cleared 6/23/2022 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 7/19/2022 LEE GUILBEAUX
Sewer availability Cleared 7/25/2022 LEE GUILBEAUX
Building over 36-ft Cleared 8/1/2022 CALOSHA APPROVED
"Q" conditions Cleared 8/30/2022 LOUIS ORTEGA
"T" removal Cleared 8/30/2022 LOUIS ORTEGA
CPC Cleared 8/30/2022 LOUIS ORTEGA
Frnt yard landscape/Water mgmt Cleared 8/30/2022 LOUIS ORTEGA
Miscellaneous Cleared 8/30/2022 LOUIS ORTEGA
Opn space landscape/Water mgmt Cleared 8/30/2022 LOUIS ORTEGA
Site Plan review Cleared 8/30/2022 LOUIS ORTEGA
ZA Case Cleared 8/30/2022 LOUIS ORTEGA

Contact Information

Architect El, Bayar, Sami M; Lic. No.: C26080 22834 BRENFORD STREET      WOODLAND HILLS, CA 91364
Contractor Hy-Max Building Corp; Lic. No.: 702339-B 425 W BROADWAY #410      GLENDALE, CA 91204
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 9/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 9/27/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/3/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/4/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 11/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/7/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/9/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/14/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/16/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/18/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/18/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/21/2022 Approved DANNY RODRIGUEZ
Piling/Pier/Caisson 11/21/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/22/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/23/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/29/2022 Approved JOHN KITCKO
Deputy Reinf. Masonry 11/29/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/29/2022 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 11/29/2022 Partial Approval JOHN KITCKO
Piling/Pier/Caisson 11/29/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 11/30/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/30/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 11/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/1/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/1/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/2/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/2/2022 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/5/2022 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/5/2022 No Access for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 12/5/2022 No Access for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/5/2022 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/7/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/7/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 12/7/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/8/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/9/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/9/2022 Approved DANNY RODRIGUEZ
Green Building Rough 12/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 12/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 12/9/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 12/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/15/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/15/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 12/15/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/16/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/19/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/21/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/22/2022 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/23/2022 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/27/2022 Approved JOHN KITCKO
Special/Order Compliance 1/11/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/23/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/24/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/25/2023 Approved DANNY RODRIGUEZ
Green Building Rough 1/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 1/25/2023 Partial Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/25/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/26/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/27/2023 Approved DANIEL VARNUM
Footing/Foundation/Slab 1/27/2023 Partial Approval DANIEL VARNUM
Piling/Pier/Caisson 1/27/2023 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 1/31/2023 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 1/31/2023 Conditional Approval STEVEN LEVITT
Deputy Reinf. Masonry 2/1/2023 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 2/1/2023 Conditional Approval STEVEN LEVITT
Deputy Reinf. Masonry 2/2/2023 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 2/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 2/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 2/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/2/2023 Partial Approval DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Not Ready DANNY RODRIGUEZ
Special/Order Compliance 2/2/2023 Partial Approval STEVEN LEVITT
Verify Sprinkler Sign Off 2/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/3/2023 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 2/3/2023 Conditional Approval STEVEN LEVITT
Deputy Reinf. Masonry 2/7/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/8/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/9/2023 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/13/2023 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 2/14/2023 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 2/14/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/17/2023 Partial Approval DANIEL VARNUM
Reinforced Concrete Frame 2/17/2023 Not Ready for Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 2/22/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 2/22/2023 Approved BRIAN KELLY
Excavation/Setback/Form/Re-Bar 3/9/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/9/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/10/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/10/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/10/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/10/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/19/2023 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 4/25/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/26/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/3/2023 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/5/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/8/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/9/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 6/13/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/14/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/14/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 6/15/2023 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 7/11/2023 Not Ready for Inspection BRIAN KELLY
Verify Sprinkler Sign Off 7/11/2023 Not Ready for Inspection BRIAN KELLY
Wood Frame 7/11/2023 Not Ready for Inspection BRIAN KELLY
Deputy Wood Construction 7/12/2023 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval BRIAN KELLY
Green Building Rough 7/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 9/18/2023 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 9/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 9/18/2023 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 9/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 9/25/2023 Conditional Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 10/5/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/5/2023 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 10/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 11/1/2023 Approved DANNY RODRIGUEZ
Green Building Rough 11/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/6/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 11/6/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 11/9/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/9/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 11/9/2023 Partial Approval DANNY RODRIGUEZ
Wood Frame 11/13/2023 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Inspection DANNY RODRIGUEZ
Insulation 11/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 11/17/2023 Partial Approval DANNY RODRIGUEZ
Insulation 11/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 11/21/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Not Ready for Inspection BRIAN KELLY
Wood Frame 11/28/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Approval CAMERON CHABAN
Insulation 12/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 12/5/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 12/11/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 12/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/18/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 12/18/2023 Partial Approval DANNY RODRIGUEZ
Insulation 12/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 1/8/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 1/10/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 1/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/19/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/19/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/19/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/2/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 2/2/2024 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 2/7/2024 Partial Approval DANNY RODRIGUEZ
Insulation 2/14/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 2/16/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/16/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/16/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/21/2024 Not Ready for Inspection ANDREW DORSO
Verify Sprinkler Sign Off 2/21/2024 Not Ready for Inspection ANDREW DORSO
Wood Frame 2/21/2024 Not Ready for Inspection ANDREW DORSO
Green Building Rough 2/26/2024 Not Ready for Inspection ANDREW DORSO
Verify Sprinkler Sign Off 2/26/2024 Partial Inspection ANDREW DORSO
Wood Frame 2/26/2024 Partial Inspection ANDREW DORSO
Drywall Nailing 2/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/28/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/28/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 2/28/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/29/2024 Partial Approval DANNY RODRIGUEZ
Wood Frame 2/29/2024 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 3/4/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 3/4/2024 Partial Inspection GREGORY POMISH
Wood Frame 3/4/2024 Partial Approval GREGORY POMISH
Wood Frame 3/5/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/6/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/7/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/7/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/7/2024 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 3/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/11/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/11/2024 Partial Approval DANNY RODRIGUEZ
Insulation 3/12/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/15/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/15/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/19/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/26/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/26/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/27/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/29/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/1/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/1/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/3/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/3/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 4/8/2024 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 4/10/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/12/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/17/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/22/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/23/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/23/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/25/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/25/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/30/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/30/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/30/2024 Partial Approval DANNY RODRIGUEZ
Insulation 5/1/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/6/2024 Not Ready for Inspection MARTIN TAVITIAN
Insulation 5/7/2024 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 5/9/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/9/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/10/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/14/2024 Partial Approval DANNY RODRIGUEZ
Insulation 5/14/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/20/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/21/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/21/2024 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 5/22/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/24/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 5/28/2024 Partial Approval DEANDRE HOFFMAN
Light Gage Steel Frame 5/30/2024 Partial Approval GREGORY POMISH
Drywall Nailing 6/4/2024 Partial Approval ROBERT DAVIS
Green Building Rough 6/4/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 6/4/2024 Partial Inspection BRIAN KELLY
Drywall Nailing 6/5/2024 Partial Approval ROBERT DAVIS
Green Building Rough 6/6/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 6/6/2024 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 6/7/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 6/11/2024 Partial Approval ROBERT DAVIS
Green Building Rough 6/11/2024 Approved ROBERT DAVIS
Light Gage Steel Frame 6/12/2024 Corrections Issued ROBERT DAVIS
Drywall Nailing 6/13/2024 Partial Approval DEANDRE HOFFMAN
Light Gage Steel Frame 6/14/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 6/20/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/20/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/21/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/26/2024 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 6/28/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/1/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/3/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/9/2024 Partial Approval DANNY RODRIGUEZ
Insulation 7/9/2024 Partial Approval DANNY RODRIGUEZ
Insulation 7/10/2024 Partial Approval DANNY RODRIGUEZ
Insulation 7/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/15/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/29/2024 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/29/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 7/31/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/5/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/13/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/16/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/20/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 8/21/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/23/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/27/2024 Partial Approval DANNY RODRIGUEZ
Insulation 8/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 9/13/2024 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 9/18/2024 Partial Inspection DANNY RODRIGUEZ
Insulation 9/27/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/16/2024 Partial Inspection ANDREW DORSO
Special/Order Compliance 11/7/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Rec and Parks Fee Memo 11/18/2024 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 12/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 12/6/2024 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/6/2025 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 1/9/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/13/2025 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 1/17/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 2/19/2025 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/28/2025 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 5/5/2025 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 6/2/2025 Partial Inspection ROBERT DAVIS
Final 6/2/2025 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 6/2/2025 Approved ROBERT DAVIS
Green Building Final 6/2/2025 Partial Inspection ROBERT DAVIS
Reinforced Concrete Frame 6/2/2025 Partial Inspection ROBERT DAVIS
Reinforced Masonry Frame 6/2/2025 Partial Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 6/2/2025 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 6/2/2025 Partial Inspection ROBERT DAVIS
Wood Frame 6/2/2025 Partial Inspection ROBERT DAVIS
Green Building Final 6/4/2025 Approved ROBERT DAVIS
Special/Order Compliance 6/4/2025 Corrections Issued ROBERT DAVIS
Verify Sprinkler Sign Off 6/4/2025 Approved ROBERT DAVIS
Special/Order Compliance 6/6/2025 Corrections Issued ROBERT DAVIS
Drywall Nailing 6/11/2025 Approved ROBERT DAVIS
Final 6/11/2025 OK for TCO ROBERT DAVIS
Reinforced Concrete Frame 6/11/2025 Approved ROBERT DAVIS
Reinforced Masonry Frame 6/11/2025 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved ROBERT DAVIS
Smoke Detectors 6/11/2025 Approved ROBERT DAVIS
Special/Order Compliance 6/11/2025 Partial Inspection BRIAN KELLY
Verify Rec and Parks Fee Memo 6/11/2025 Approved ROBERT DAVIS
Wood Frame 6/11/2025 Approved ROBERT DAVIS
Final 10/1/2025 OK to Issue CofO ROBERT DAVIS