1033 W 85TH ST 90044

Certificate Information: 1033 W 85TH ST 90044

Application / Permit
21010-10000-03670
Plan Check / Job No.
B21LA13765
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY ADU AT REAR OF LOT.
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 11/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 JOE VO
Corrections Issued 8/21/2021 JOE VO
Quality Review Completed 8/31/2021 MICHAEL PEREZ
Applicant returned to address corrections 4/20/2022 JOE VO
Plan Check Approved 6/2/2022 JOE VO
Issued 6/10/2022 APPLICANT
CofO in Progress 11/21/2025 JOHN QUINTANILLA
Permit Finaled 11/22/2025 DEROLD HAUFF
CofO Issued 11/22/2025 DEROLD HAUFF
Permit Finaled 11/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/10/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/6/2021 CINDY QI
Sewer availability Cleared 12/6/2021 CINDY QI
Low Impact Development Cleared 3/24/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/4/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 5/11/2022 CINDY JOSSELYN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/15/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 5/15/2023 Partial Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/17/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/17/2023 Approved MICHAEL LEWIS
Underground Mechanical 5/26/2023 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 6/1/2023 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 6/1/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/1/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/5/2023 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 6/5/2023 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval STUART CHAPMAN
Insulation 6/7/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 7/24/2023 Approved MICHAEL LEWIS
HVAC-Rough 7/24/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 7/24/2023 Approved MICHAEL LEWIS
Deputy Wood Construction 7/25/2023 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 7/27/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 7/27/2023 Approved MICHAEL LEWIS
Drywall Nailing 8/2/2023 Not Ready for Inspection MICHAEL LEWIS
Insulation 8/2/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/2/2023 Approved MICHAEL LEWIS
Shower Pan 8/2/2023 Not Ready for Inspection MICHAEL LEWIS
Drywall Nailing 8/9/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/9/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/15/2023 Approved MICHAEL LEWIS
Shower Pan 8/15/2023 Approved MICHAEL LEWIS
Sewer 1/16/2024 Approved MICHAEL LEWIS
Underground Mechanical 1/16/2024 Approved MICHAEL LEWIS
Underground Mechanical 12/3/2024 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 12/27/2024 Approved JOHN QUINTANILLA
Final 12/27/2024 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 12/27/2024 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 12/27/2024 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 12/27/2024 Approved JOHN QUINTANILLA
ELECTRICAL-Final 12/31/2024 Approved JOHN QUINTANILLA
HVAC-Final 12/31/2024 Approved JOHN QUINTANILLA
PLUMBING-Final 12/31/2024 Approved JOHN QUINTANILLA
Final 3/11/2025 Conditional Approval JOHN QUINTANILLA
Service/Power Release 3/11/2025 Approved JOHN QUINTANILLA
Final 11/19/2025 OK to Issue CofO JOHN QUINTANILLA