1033 W 85TH ST 90044
Certificate Information: 1033 W 85TH ST 90044
- Application / Permit
- 21010-10000-03670
- Plan Check / Job No.
- B21LA13765
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ADU AT REAR OF LOT.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 11/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | JOE VO |
| Corrections Issued | 8/21/2021 | JOE VO |
| Quality Review Completed | 8/31/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 4/20/2022 | JOE VO |
| Plan Check Approved | 6/2/2022 | JOE VO |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 11/21/2025 | JOHN QUINTANILLA |
| Permit Finaled | 11/22/2025 | DEROLD HAUFF |
| CofO Issued | 11/22/2025 | DEROLD HAUFF |
| Permit Finaled | 11/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2021 | CINDY QI |
| Sewer availability | Cleared | 12/6/2021 | CINDY QI |
| Low Impact Development | Cleared | 3/24/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 5/11/2022 | CINDY JOSSELYN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/15/2023 | Partial Inspection | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/17/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/17/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/26/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/1/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/1/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 6/1/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/5/2023 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 6/5/2023 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/7/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/24/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 7/24/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/24/2023 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 7/25/2023 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/27/2023 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 7/27/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/2/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Insulation | 8/2/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/2/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 8/2/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Drywall Nailing | 8/9/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/9/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/15/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 8/15/2023 | Approved | MICHAEL LEWIS |
| Sewer | 1/16/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/16/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/3/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 12/27/2024 | Approved | JOHN QUINTANILLA |
| Final | 12/27/2024 | Corrections Issued | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2024 | SGSOV Approved | JOHN QUINTANILLA |
| Service/Power Release | 12/27/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 12/27/2024 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 12/31/2024 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 12/31/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 12/31/2024 | Approved | JOHN QUINTANILLA |
| Final | 3/11/2025 | Conditional Approval | JOHN QUINTANILLA |
| Service/Power Release | 3/11/2025 | Approved | JOHN QUINTANILLA |
| Final | 11/19/2025 | OK to Issue CofO | JOHN QUINTANILLA |