1058 1/2 S WINDSOR BLVD 90019
Certificate Information: 1058 1/2 S WINDSOR BLVD 90019
- Application / Permit
- 21010-10000-03668
- Plan Check / Job No.
- B21LA13757
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY A.D.U. PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/31/2021 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| Plan Check Approved | 5/20/2022 | RICARDO RAMIREZ |
| Issued | 6/22/2022 | APPLICANT |
| CofO in Progress | 6/1/2023 | JEFFREY MEAD |
| Permit Finaled | 6/6/2023 | DEROLD HAUFF |
| CofO Issued | 6/6/2023 | DEROLD HAUFF |
| Permit Finaled | 6/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2021 | WALLIE JONG |
| Sewer availability | Cleared | 12/30/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 1/28/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | WALLIE JONG |
| HPOZ | Cleared | 3/23/2022 | AMANDA KAINER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/3/2022 | Corrections Issued | JEFFREY MEAD |
| METHANE-Barrier | 8/3/2022 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 8/3/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 8/3/2022 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/15/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/8/2022 | Partial Approval | JEFFREY MEAD |
| Wood Frame | 9/8/2022 | Partial Approval | JEFFREY MEAD |
| Insulation | 9/14/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/12/2022 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 12/12/2022 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 12/12/2022 | Approved | JEFFREY MEAD |
| Wood Frame | 12/12/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 12/22/2022 | Approved | JEFFREY MEAD |
| Wood Frame | 12/22/2022 | Approved | JEFFREY MEAD |
| Insulation | 12/29/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 1/5/2023 | Approved | JEFFREY MEAD |
| Pre-Inspection | 1/5/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | JEFFREY MEAD |
| Final | 1/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 1/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 1/24/2023 | Approved | JEFFREY MEAD |
| METHANE-Final | 1/24/2023 | Approved | JEFFREY MEAD |
| METHANE-Rough | 1/24/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 1/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 1/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 1/24/2023 | Approved | JEFFREY MEAD |
| Final | 3/16/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/16/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 3/16/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 3/16/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 3/30/2023 | Approved | JEFFREY MEAD |
| Final | 3/30/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/30/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 3/30/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 3/30/2023 | Approved | JEFFREY MEAD |
| Service/Power Release | 3/30/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 3/30/2023 | Approved | JEFFREY MEAD |
| Final | 4/12/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 4/12/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 5/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 5/24/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 6/1/2023 | OK to Issue CofO | JEFFREY MEAD |
| Service/Power Release | 6/1/2023 | Approved | JEFFREY MEAD |