448 E 118TH ST 90061
Certificate Information: 448 E 118TH ST 90061
- Application / Permit
- 21010-10000-03662
- Plan Check / Job No.
- B21LA13733
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING OVER 4-CAR GARAGE (REAR BUILDING) 2 OF 2
- Permit Issued
- Issued on 3/16/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | HANS SANTIAGO |
| Corrections Issued | 8/16/2021 | HANS SANTIAGO |
| Quality Review Completed | 8/19/2021 | SAI KHUM |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 9/23/2021 | HANS SANTIAGO |
| Plan Check Approved | 9/27/2021 | ANDREW SANTIAGO |
| Issued | 3/16/2023 | APPLICANT |
| CofO in Progress | 8/23/2023 | JOHN KLARIN |
| Permit Finaled | 10/18/2023 | ANSON MAGLASANG |
| CofO Issued | 10/18/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/18/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2021 | WALLIE JONG |
| Permit | Cleared | 9/1/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 9/2/2021 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 9/9/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 9/16/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 9/21/2021 | WALLIE JONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | JOHN KLARIN |
| HVAC-Rough | 6/1/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/1/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/5/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/5/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 6/5/2023 | Approved | JOHN KLARIN |
| Insulation | 6/5/2023 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 6/5/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/5/2023 | Approved | JOHN KLARIN |
| Insulation | 6/7/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/20/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/20/2023 | Approved | JAMES CHAVEZ |
| Sewer | 7/18/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 7/18/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/3/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 8/18/2023 | Approved | JOHN KLARIN |
| Final | 8/18/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/18/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 8/18/2023 | Approved | JOHN KLARIN |
| MERV13>=Final | 8/18/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 8/18/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 8/18/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 8/18/2023 | Approved | JOHN KLARIN |
| Final | 8/22/2023 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 8/22/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 8/31/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 10/5/2023 | Approved | JOHN KLARIN |