1223 1/4-1/2 W 25TH ST 90007

Certificate Information: 1223 1/4-1/2 W 25TH ST 90007

Application / Permit
21010-10000-03658
Plan Check / Job No.
B21LA13716
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY (2) UNIT ADU DUPLEX AT REAR OF LOT. methane buffer
Permit Issued
Issued on 12/3/2021
Issuing Office
Current Status
CofO Issued on 6/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 JOE VO
Corrections Issued 8/21/2021 JOE VO
Quality Review Completed 8/30/2021 MICHAEL PEREZ
Plan Check Approved 12/1/2021 JOE VO
Issued 12/3/2021 APPLICANT
CofO in Progress 5/17/2022 ALEJANDRO DE ARTOLA
Permit Finaled 6/4/2022 DEROLD HAUFF
CofO Issued 6/4/2022 DEROLD HAUFF
Permit Finaled 6/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/8/2021 THOMAS LANG
Sewer availability Cleared 9/8/2021 THOMAS LANG
Community Plan Implem. Overlay Cleared 9/13/2021 JEANIE LAM
Community Plan Implem. Overlay Cleared 9/16/2021 MOHAMMAD HASAN
Community Plan Implem. Overlay Cleared 9/21/2021 ADRIAN SANCHEZ
Low Impact Development Cleared 9/24/2021 KHAING AYE
Community Plan Implem. Overlay Cleared 10/5/2021 TORI CHEN
Roof/Waste drainage to street Cleared 10/5/2021 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 11/2/2021 RAFAEL FONTES
ZI Cleared 11/2/2021 RAFAEL FONTES
Hydrant and Access approval Cleared 11/19/2021 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: NA65104       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/22/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/13/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/13/2022 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/20/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 2/8/2022 Conditional Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/15/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 2/16/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/23/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/23/2022 Approved ALEJANDRO DE ARTOLA
Shower Pan 2/23/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/25/2022 Approved ALEJANDRO DE ARTOLA
Insulation 2/25/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 2/25/2022 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 2/25/2022 Approved ALEJANDRO DE ARTOLA
Insulation 2/28/2022 Approved ALEJANDRO DE ARTOLA
Wood Frame 2/28/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 3/2/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/21/2022 Approved ALEJANDRO DE ARTOLA
Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/21/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/21/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 4/21/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 4/21/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 4/21/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 4/21/2022 Approved ALEJANDRO DE ARTOLA
Final 4/28/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/16/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
PLUMBING-Final 5/16/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 5/19/2022 Approved ALEJANDRO DE ARTOLA