10049-10051 W HILLGROVE DR 90210
Certificate Information: 10049-10051 W HILLGROVE DR 90210
- Application / Permit
- 21010-10000-03656
- Plan Check / Job No.
- B21LA13711
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New detached ADU 34'X17'. A 514 sq. ft. 1 bedroom, 1 bathroom Accessory Dwelling Unit to be built in the rear of the property.
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 8/28/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/11/2021 | YOUNG KIM |
| Applicant returned to address corrections | 10/27/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 11/13/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 12/1/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 2/1/2022 | ARSALAN SHABESTARI |
| Issued | 2/10/2022 | APPLICANT |
| CofO in Progress | 11/7/2024 | SEAN HAUPT |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/3/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/3/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/3/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/3/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/3/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | DINAH GARIN |
| Sewer availability | Cleared | 9/8/2021 | DINAH GARIN |
| Tract Map conditions | Cleared | 9/17/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 9/17/2021 | DANIEL CORONADO |
| ZI | Cleared | 9/17/2021 | DANIEL CORONADO |
| GPI Written Notices | Cleared | 11/15/2021 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 11/15/2021 | ARSALAN SHABESTARI |
| Hydrant and Access approval | Cleared | 11/20/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/20/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | DINAH GARIN |
Contact Information
| Architect | Barber,, Charles Timothy; Lic. No.: NA29232 | , |
| Contractor | Chelsea Construction Corp; Lic. No.: 710035-B | 4529 ANGELES CREST HWY 103 LA CANADA, CA 91011 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 2/8/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 2/21/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 2/21/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/8/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/15/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 6/5/2023 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Partial Approval | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 7/14/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Elec/Plmb/HVAC | 7/21/2023 | Corrections Issued | BRENDAN LOONEY |
| Pre-Inspection | 7/31/2023 | Partial Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 7/31/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 8/25/2023 | Partial Approval | BRENDAN LOONEY |
| Sewer | 8/25/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 9/20/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 9/28/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | BRENDAN LOONEY |
| Insulation | 10/10/2023 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 10/13/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 1/16/2024 | Corrections Issued | BRENDAN LOONEY |
| Shower Pan | 1/19/2024 | Approved | BRENDAN LOONEY |
| Final | 6/6/2024 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 6/6/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | SEAN HAUPT |
| Service/Power Release | 6/6/2024 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 6/6/2024 | Approved | SEAN HAUPT |
| Final | 11/5/2024 | OK to Issue CofO | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 11/5/2024 | Approved | SEAN HAUPT |