1414-1416 W 36TH ST 90018

Certificate Information: 1414-1416 W 36TH ST 90018

Application / Permit
21010-10000-03623
Plan Check / Job No.
B21LA13592
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 MAHNAZ NOURHASHEMI
Corrections Issued 9/3/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 9/15/2021 JASON HEALEY
Plan Check Approved 5/4/2022 MAHNAZ NOURHASHEMI
Issued 5/4/2022 APPLICANT
CofO in Progress 7/6/2023 SABAS ALONSO
Permit Finaled 7/18/2023 DEROLD HAUFF
CofO Issued 7/18/2023 DEROLD HAUFF
Permit Finaled 7/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/15/2021 WALLIE JONG
Permit Cleared 12/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/17/2021 WALLIE JONG
Sewer availability Cleared 12/21/2021 WALLIE JONG
Hydrant and Access approval Cleared 2/12/2022 RUEL COLE
Low Impact Development Cleared 4/1/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/7/2022 WALLIE JONG
Trees in Parkway Cleared 4/29/2022 ADALBERTO VERA

Contact Information

Contractor Tre Development Llc; Lic. No.: 1075573-B 2905 S VERMONT AVE #204      LOS ANGELES, CA 90007
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/22/2022 Partial Approval SABAS ALONSO
Underground Mechanical 6/24/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/1/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 7/1/2022 Approved SABAS ALONSO
METHANE-Barrier 7/1/2022 Approved SABAS ALONSO
METHANE-Subgrade 7/1/2022 Approved SABAS ALONSO
Deputy Reinf. Concrete 7/27/2022 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 8/1/2022 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 8/2/2022 Conditional Approval SABAS ALONSO
Deputy Drilled-In Anchors 8/15/2022 Conditional Approval RYAN SALAZAR
Deputy Steel/Welding 8/31/2022 Conditional Approval SABAS ALONSO
Deputy Drilled-In Anchors 9/2/2022 Conditional Approval MICHAEL LEWIS
Deputy Wood Construction 9/8/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval SABAS ALONSO
Deputy Wood Construction 10/5/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval SABAS ALONSO
Deputy Wood Construction 12/22/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Approved SABAS ALONSO
HVAC-Rough 1/3/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 1/11/2023 Approved SABAS ALONSO
PLUMBING-Rough 1/13/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/7/2023 Conditional Approval SABAS ALONSO
Green Building Rough 2/7/2023 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 2/7/2023 Corrections Issued SABAS ALONSO
METHANE-Rough 2/7/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 2/7/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 2/13/2023 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/17/2023 Approved SABAS ALONSO
Green Building Rough 2/17/2023 Approved SABAS ALONSO
Insulation 3/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 3/15/2023 Approved SABAS ALONSO
Drywall Nailing 3/29/2023 Corrections Issued SABAS ALONSO
Drywall Nailing 4/3/2023 Approved SABAS ALONSO
Underground Mechanical 4/25/2023 Approved SABAS ALONSO
Gas Test 4/27/2023 Approved SABAS ALONSO
Service/Power Release 6/5/2023 Partial Inspection SABAS ALONSO
ELECTRICAL-Final 6/30/2023 Corrections Issued SABAS ALONSO
Final 6/30/2023 Corrections Issued SABAS ALONSO
Green Building Final 6/30/2023 Approved SABAS ALONSO
HVAC-Final 6/30/2023 Approved SABAS ALONSO
PLUMBING-Final 6/30/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Ready SABAS ALONSO
Service/Power Release 6/30/2023 Approved SABAS ALONSO
Smoke Detectors 6/30/2023 Approved SABAS ALONSO
Final 7/5/2023 OK to Issue CofO SABAS ALONSO
Green Building Final 7/5/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 7/5/2023 Approved SABAS ALONSO