1431 1/2 S HAUSER BLVD 90019
Certificate Information: 1431 1/2 S HAUSER BLVD 90019
- Application / Permit
- 21010-10000-03614
- Plan Check / Job No.
- B21LA13504
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. New accessory dwelling unit by Installing a two-bedroom RADCO Approved Factory Built Housing Accessory Dwelling Unit over a raised floor foundation. LADBS ADU Standard Plan ADU30. FBH Per: RAD-31-1029. Per CA Govt. Code 65852.2(e)(1)(D)
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 2/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | MONICA RAMIREZ |
| Corrections Issued | 7/22/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/22/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/13/2022 | MONICA RAMIREZ |
| Plan Check Approved | 1/18/2022 | MONICA RAMIREZ |
| Issued | 1/19/2022 | APPLICANT |
| CofO in Progress | 12/5/2022 | JOSE AVILA |
| No Progress | 2/16/2023 | JOSE AVILA |
| CofO in Progress | 2/16/2023 | JOSE AVILA |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
| CofO Issued | 2/19/2023 | DEROLD HAUFF |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/2/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 9/14/2021 | TINA MIRANDA |
| Low Impact Development | Cleared | 1/4/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/4/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 1/18/2022 | MICHAEL SOTO |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | , |
| Engineer | Farish,, William Crawford; Lic. No.: C30123 | 19432 CASTLEWOOD CR HUNTINGTON BEACH, CA 92648 |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/15/2022 | Corrections Issued | JOSE AVILA |
| Sewer | 3/15/2022 | Approved | JOSE AVILA |
| Underground Mechanical | 3/15/2022 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 3/24/2022 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 4/18/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 4/18/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 4/18/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 4/18/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 4/28/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 4/28/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/28/2022 | Approved | JOSE AVILA |
| Sewer | 5/16/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/10/2022 | No Access for Inspection | STUART CHAPMAN |
| HVAC-Final | 6/10/2022 | No Access for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 7/29/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/4/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 8/4/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Not Ready | JOSE AVILA |
| ELECTRICAL-Final | 8/30/2022 | Approved | JOSE AVILA |
| HVAC-Final | 8/30/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 8/30/2022 | Approved | JOSE AVILA |
| Pre-Inspection | 8/30/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 9/26/2022 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 10/12/2022 | Approved | JOSE AVILA |
| Service/Power Release | 10/12/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | JOSE AVILA |
| Final | 11/3/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/3/2022 | Approved | JOSE AVILA |
| Green Building Final | 11/3/2022 | Partial Approval | JOSE AVILA |
| HVAC-Final | 11/3/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Barrier | 11/3/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 11/3/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/3/2022 | Approved | JOSE AVILA |
| Final | 11/29/2022 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 11/29/2022 | Approved | JOSE AVILA |