1056 E AMOROSO PL 90291

Certificate Information: 1056 E AMOROSO PL 90291

Application / Permit
21010-10000-03611
Plan Check / Job No.
B21LA13479
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) STATE APPROVED FBH 695 SQ.FT. DETACHED ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 7/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2021 APPLICANT
Assigned to Plan Check Engineer 7/23/2021 DANIEL SANJUAN
Corrections Issued 7/24/2021 DANIEL SANJUAN
Applicant returned to address corrections 2/2/2022 LUKE GONZALES
Building Plans Picked Up 2/4/2022 APPLICANT
Plan Check Approved 3/1/2022 FERNANDO FLORES
Issued 3/2/2022 APPLICANT
CofO in Progress 7/25/2022 RICHARD STEINBACH
Permit Finaled 7/25/2022 DANIEL ORRANTE
CofO Issued 7/25/2022 DANIEL ORRANTE
Permit Finaled 7/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/16/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/16/2021 SAUL GARCIA
Sewer availability Cleared 9/16/2021 SAUL GARCIA
Low Impact Development Cleared 11/30/2021 TA ANH
Roof/Waste drainage to street Cleared 12/15/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 1/15/2022 GILBERT URREA
Specific Plan Cleared 2/16/2022 PEDRO AYALA

Contact Information

Contractor Cover Technologies Inc; Lic. No.: 1039029-B 1219 W 135TH STREET      GARDENA, CA 90247
Engineer Nielsen,, Gregory Michael Wat; Lic. No.: S6653 4991 WESTPARK DR      VALLEY VILLAGE, CA 91601

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/23/2022 Partial Approval JESUS RODRIGUEZ
Sewer 4/23/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 4/23/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 4/29/2022 Approved KENNETH NAGLE
Deputy Reinf. Concrete 5/2/2022 No Access for Inspection DAVID FEILER
Underground Mechanical 5/5/2022 Partial Approval KENNETH NAGLE
Deputy Drilled-In Anchors 5/16/2022 Conditional Approval STEPHANIE SWANSON
Final 7/15/2022 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 7/15/2022 Approved KENNETH NAGLE
Smoke Detectors 7/15/2022 Approved KENNETH NAGLE
BUILDING-Rough-Frame 7/20/2022 Approved RICHARD STEINBACH
ELECTRICAL-Final 7/20/2022 Approved RICHARD STEINBACH
Final 7/20/2022 Not Ready for Inspection RICHARD STEINBACH
Green Building Final 7/20/2022 Approved RICHARD STEINBACH
Green Building Rough 7/20/2022 Approved RICHARD STEINBACH
HVAC-Final 7/20/2022 Approved RICHARD STEINBACH
PLUMBING-Final 7/20/2022 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Approved RICHARD STEINBACH
Verify Sprinkler Sign Off 7/20/2022 Approved RICHARD STEINBACH
Final 7/25/2022 OK to Issue CofO RICHARD STEINBACH