1340-1340 1/2 W 35TH PL 90007

Certificate Information: 1340-1340 1/2 W 35TH PL 90007

Application / Permit
21010-10000-03537
Plan Check / Job No.
B21LA13216
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 4-STORY DUPLEX W/ ATTACHED 4-CAR GARAGE (REAR BLDG)
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 MAHNAZ NOURHASHEMI
Corrections Issued 9/3/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 9/14/2021 JASON HEALEY
Building Plans Picked Up 9/20/2021 APPLICANT
Plan Check Approved 3/9/2022 MAHNAZ NOURHASHEMI
Issued 3/10/2022 APPLICANT
CofO in Progress 3/18/2024 SABAS ALONSO
CofO Issued 3/18/2024 DEROLD HAUFF
Permit Finaled 3/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/13/2021 CECILIO NAVARRO
Sewer availability Cleared 10/27/2021 PAMELA TENEZA
Frnt yard landscape/Water mgmt Cleared 11/9/2021 DANIEL CORONADO
ZI Cleared 11/9/2021 DANIEL CORONADO
Permit Cleared 12/14/2021 JEANETTE VONG
Low Impact Development Cleared 12/23/2021 KHAING AYE
Roof/Waste drainage to street Cleared 12/28/2021 JEANETTE VONG
Trees in Parkway Cleared 1/5/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 1/14/2022 GILBERT URREA
Flood clearance Cleared 2/23/2022 BRYAN GATHUKA
Building over 36-ft Cleared 3/9/2022 CALOSHA APPROVED

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/6/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 5/23/2022 Partial Approval SABAS ALONSO
FLOOD-Elevation Certificate 5/23/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 5/23/2022 Partial Approval SABAS ALONSO
METHANE-Barrier 5/23/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 5/23/2022 Not Ready for Inspection SABAS ALONSO
FLOOD-Elevation Certificate 6/20/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 6/20/2022 Partial Approval SABAS ALONSO
METHANE-Barrier 6/20/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 6/20/2022 Not Ready for Inspection SABAS ALONSO
FLOOD-Elevation Certificate 7/12/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 7/12/2022 Approved SABAS ALONSO
METHANE-Barrier 7/12/2022 Approved SABAS ALONSO
METHANE-Subgrade 7/12/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval SABAS ALONSO
Deputy Wood Construction 2/21/2023 Conditional Approval SABAS ALONSO
Interior/Exterior Lathing 2/24/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 3/28/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 3/28/2023 Approved SABAS ALONSO
FLOOD-Proofing Certificate 3/28/2023 Approved SABAS ALONSO
Green Building Rough 3/28/2023 Approved SABAS ALONSO
HVAC-Rough 3/28/2023 Approved SABAS ALONSO
METHANE-Rough 3/28/2023 Approved SABAS ALONSO
PLUMBING-Rough 3/28/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 3/28/2023 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/10/2023 Conditional Approval SABAS ALONSO
Verify Sprinkler Sign Off 4/10/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 4/14/2023 Approved SABAS ALONSO
Insulation 4/14/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/14/2023 Approved SABAS ALONSO
Drywall Nailing 4/26/2023 Not Ready for Inspection BRENDAN MORELLI
Drywall Nailing 4/28/2023 Approved SABAS ALONSO
ELECTRICAL-Final 10/6/2023 Corrections Issued SABAS ALONSO
Gas Test 10/6/2023 Approved SABAS ALONSO
PLUMBING-Final 10/6/2023 Approved SABAS ALONSO
Service/Power Release 10/6/2023 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 10/6/2023 Approved SABAS ALONSO
Final 11/8/2023 Corrections Issued SABAS ALONSO
Green Building Final 11/8/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved SABAS ALONSO
Service/Power Release 11/8/2023 Approved SABAS ALONSO
Final 2/28/2024 Not Ready for Inspection SABAS ALONSO
Final 3/12/2024 Corrections Issued SABAS ALONSO
Final 3/15/2024 OK to Issue CofO SABAS ALONSO