14899 W ROUND VALLEY DR 91403

Certificate Information: 14899 W ROUND VALLEY DR 91403

Application / Permit
21010-10000-03530
Plan Check / Job No.
B21LA13203
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 3-STORY + BASEMENT SINGLE FAMILY DWELLING WITH AN ATTACHED 3-CAR GARAGE. ***SEE COMMENTS*** 1 OF 2
Permit Issued
Issued on 9/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 MICHAEL LOPEZ
Corrections Issued 8/19/2021 MICHAEL LOPEZ
Quality Review Completed 8/25/2021 KEN GILL
Building Plans Picked Up 8/30/2021 APPLICANT
Applicant returned to address corrections 3/15/2022 MICHAEL LOPEZ
Applicant returned to address corrections 3/17/2022 MICHAEL LOPEZ
Applicant returned to address corrections 5/24/2022 MICHAEL LOPEZ
Applicant returned to address corrections 6/30/2022 MICHAEL LOPEZ
Plan Check Approved 7/19/2022 MICHAEL LOPEZ
No Progress 7/29/2022 MICHAEL LOPEZ
Plan Check Approved 9/21/2022 MICHAEL LOPEZ
Issued 9/29/2022 APPLICANT
CofO in Progress 6/27/2025 JACK KARGODORIAN
CofO Issued 7/11/2025 RUBEN SALAS
Permit Finaled 7/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2021 CARLOS AGUILERA
Miscellaneous Cleared 9/13/2021 CARLOS AGUILERA
Permit Cleared 9/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/17/2021 CARLOS AGUILERA
Sewer availability Cleared 9/17/2021 CARLOS AGUILERA
Miscellaneous Cleared 10/1/2021 RICHARD REASER
Hydrant and Access approval Cleared 12/28/2021 GILBERT URREA
Trees in Parkway Cleared 1/6/2022 ADALBERTO VERA
BHO/Hillside ordinance Cleared 1/10/2022 CARLOS AGUILERA
Low Impact Development Cleared 1/27/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 2/1/2022 ABEL CASILLAS
GPI Written Notices Cleared 3/15/2022 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 3/15/2022 MANUEL TEJADA
Encroachment in public way Cleared 5/5/2022 CARLOS AGUILERA
Disturb/Remove Protected Trees Cleared 9/1/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307
Engineer Haro,, Ruben; Lic. No.: C72213 355 N LANTANA ST STE 492      CAMARILLO, CA 93010
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2022 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 11/14/2022 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 11/16/2022 Partial Approval THOMAS FINNILA
Deputy Steel/Welding 11/17/2022 Conditional Approval MICHAEL SMITH
Deputy Reinf. Concrete 11/18/2022 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 11/18/2022 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 11/21/2022 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 12/12/2022 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 12/13/2022 Partial Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 12/19/2022 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 12/21/2022 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 1/25/2023 Approved THOMAS FINNILA
Piling/Pier/Caisson 1/25/2023 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 1/27/2023 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 2/21/2023 Approved THOMAS FINNILA
Piling/Pier/Caisson 2/21/2023 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 2/22/2023 Conditional Approval DAVID MATSON
Piling/Pier/Caisson 3/28/2023 Partial Approval THOMAS FINNILA
Deputy Steel/Welding 3/31/2023 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 4/4/2023 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 4/19/2023 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 5/17/2023 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 6/30/2023 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 7/21/2023 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 8/15/2023 Conditional Approval THOMAS FINNILA
Piling/Pier/Caisson 8/16/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 8/17/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 8/18/2023 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 9/8/2023 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 9/26/2023 Conditional Approval DAVID MATSON
PLUMBING-Rough 10/6/2023 Partial Approval THOMAS FINNILA
Underground Mechanical 10/23/2023 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 11/7/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 11/8/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 11/9/2023 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 11/30/2023 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 12/13/2023 Conditional Approval JUAN VALENZUELA
Deputy Shotcrete 12/14/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 12/14/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Shotcrete 12/15/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/12/2024 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/14/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/16/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/17/2024 Partial Approval THOMAS FINNILA
Deputy Shotcrete 4/19/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/7/2024 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 5/10/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 7/1/2024 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 7/2/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 8/5/2024 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 8/14/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 9/5/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/10/2024 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 9/10/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Approved CHRISTOPHE COCHRAN
Green Building Rough 9/10/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 9/10/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/19/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 9/23/2024 Approved MISAEL ESPARZA
Insulation 9/27/2024 Corrections Issued JACK KARGODORIAN
Insulation 10/2/2024 Approved JACK KARGODORIAN
Drywall Nailing 10/10/2024 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 10/10/2024 Partial Approval ROBERT GOLD
Drywall Nailing 10/25/2024 Approved JACK KARGODORIAN
Shower Pan 11/14/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/21/2024 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 4/7/2025 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Final 5/27/2025 Approved JACK KARGODORIAN
Final 5/27/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 5/27/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 5/27/2025 Approved JACK KARGODORIAN
PLUMBING-Final 5/27/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV No Gas JACK KARGODORIAN
Service/Power Release 5/27/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 5/27/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/4/2025 Approved JACK KARGODORIAN
Final 6/4/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 6/4/2025 Approved JACK KARGODORIAN
HVAC-Final 6/4/2025 Approved JACK KARGODORIAN
PLUMBING-Final 6/4/2025 Approved JACK KARGODORIAN
Service/Power Release 6/4/2025 Not Ready for Inspection JACK KARGODORIAN
Final 6/26/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 6/26/2025 Approved JACK KARGODORIAN