4968 W FIR ST 90016

Certificate Information: 4968 W FIR ST 90016

Application / Permit
21010-10000-03529
Plan Check / Job No.
B21LA13202
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1070 SQ FT DETACHED ACCESSORY DWELLING UNIT (ADU) PER ORDINANCE AND LAMC 12.22 A.33 (c) &(d).1 OF 2
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 ZAW HAN
Corrections Issued 8/11/2021 ZAW HAN
Quality Review Completed 8/18/2021 KEN GILL
Applicant returned to address corrections 11/17/2021 ZAW HAN
Plan Check Approved 11/18/2021 ZAW HAN
Issued 12/2/2021 APPLICANT
CofO in Progress 11/4/2022 STUART CHAPMAN
Permit Finaled 11/12/2022 DEROLD HAUFF
CofO Issued 11/12/2022 DEROLD HAUFF
Permit Finaled 11/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/17/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/19/2021 THOMAS LANG
Hydrant and Access approval Cleared 10/21/2021 RUEL COLE
Sewer availability Cleared 10/22/2021 THOMAS LANG
Low Impact Development Cleared 10/28/2021 TA ANH
Roof/Waste drainage to street Cleared 11/2/2021 THAN WIN
Green Code Cleared 11/18/2021 ZAW HAN

Contact Information

Contractor Builders & Son'S Inc; Lic. No.: 961171-B 8720 VENICE BLVD STE 208      LOS ANGELES, CA 90034
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/10/2022 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 5/31/2022 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 5/31/2022 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 5/31/2022 Approved STUART CHAPMAN
Shower Pan 6/9/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/17/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 6/17/2022 Approved STUART CHAPMAN
Green Building Rough 6/17/2022 Approved STUART CHAPMAN
Insulation 6/17/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/17/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 6/17/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 9/19/2022 Corrections Issued STUART CHAPMAN
Gas Test 9/19/2022 Approved STUART CHAPMAN
PLUMBING-Final 9/19/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/27/2022 Approved STUART CHAPMAN
Final 10/27/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/27/2022 Approved STUART CHAPMAN
Green Building Final 10/27/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 10/27/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 10/27/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 11/2/2022 Approved STUART CHAPMAN
Final 11/2/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 11/2/2022 Approved STUART CHAPMAN
PLUMBING-Final 11/2/2022 Approved STUART CHAPMAN
Service/Power Release 11/2/2022 Approved STUART CHAPMAN