9785 S BELLANCA AVE 90045
Certificate Information: 9785 S BELLANCA AVE 90045
- Application / Permit
- 21010-10000-03519
- Plan Check / Job No.
- B21LA13134
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- CONSTRUCTION OF 143,081 SF SPECULATIVE WAREHOUSE INCLUDES W/ OFFICE/BREAK SPACE. OFF SITE PARKING AT 5760 W ARBOR VITAE ST UNDER SEPARATE PERMIT.
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Green Plans Picked Up | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 9/15/2021 | SERGIO GUTIERREZ |
| Disabled Access Plans Picked Up | 9/15/2021 | APPLICANT |
| Quality Review Completed | 9/16/2021 | FARUK SEZER |
| Building Plans Picked Up | 9/20/2021 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 1/26/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 2/17/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 5/13/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 11/16/2022 | SERGIO GUTIERREZ |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 2/11/2025 | DERRICK SPENCER |
| No Progress | 2/14/2025 | DAVID TSAU |
| CofO in Progress | 2/14/2025 | DAVID TSAU |
| TCO Issued (Expire Date: 08-13-2025) | 2/14/2025 | HENRY BAGHDASSARIAN |
| TCO Issued (Expire Date: 01-26-2026) | 7/30/2025 | HENRY BAGHDASSARIAN |
| CofO in Progress | 2/4/2026 | DERRICK SPENCER |
| CofO in Progress | 2/13/2026 | VASIL MIHALEV |
| Permit Finaled | 3/4/2026 | VASIL MIHALEV |
| CofO Issued | 3/4/2026 | VASIL MIHALEV |
| Permit Finaled | 3/4/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 6/29/2022 | RYAN LY |
| Miscellaneous | Cleared | 6/29/2022 | RYAN LY |
| Green Code | Cleared | 6/30/2022 | AARON COSTA |
| Low Impact Development | Cleared | 6/30/2022 | SARAH YOUSSEF |
| Stormwater Pollution Mitigatn | Cleared | 6/30/2022 | SARAH YOUSSEF |
| Comm Cor/Mini-Mall | Cleared | 7/1/2022 | RYAN LY |
| Comm Cor/Mini-Mall | Cleared | 7/1/2022 | RYAN LY |
| Prkng lot landscape/Water mgmt | Cleared | 7/6/2022 | RYAN LY |
| DAS Clearance | Cleared | 7/20/2022 | SERGIO GUTIERREZ |
| Fire Marshal Fire Life Safety | Cleared | 7/20/2022 | MENOA AGHAJANI |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | CATHERINE ADROVER |
| Highway dedication | Cleared | 8/16/2022 | RAYMOND MUGAMBWA |
| Permit | Cleared | 8/30/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/31/2022 | CATHERINE ADROVER |
| Internal circulation | Cleared | 9/27/2022 | PEDRO AYALA |
| Specific Plan | Cleared | 9/28/2022 | PEDRO AYALA |
| Address approval | Cleared | 10/12/2022 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 11/4/2022 | GILBERT URREA |
| Building over 36-ft | Cleared | 11/16/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Nam,, Yong Hwan; Lic. No.: C29451 | 18831 BARDEEN AVENUE # 100 IRVINE, CA 92612 |
| Contractor | Millie And Severson General Contractors; Lic. No.: 99031-B | P O BOX 3601 LOS ALAMITOS, CA 90720 |
| Engineer | Gerges,, Rafik; Lic. No.: S5092 | 1906 W GARVEY AVE STE 200 WEST COVINA, CA 91790 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/23/2022 | Approved | DERRICK SPENCER |
| Pre-Inspection | 11/30/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/8/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/8/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/9/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/3/2023 | Partial Approval | DERRICK SPENCER |
| SWPPP-Const. Storm Water | 1/4/2023 | Completed | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 1/10/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/20/2023 | Conditional Approval | DERRICK SPENCER |
| Green Building Rough | 1/20/2023 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 1/20/2023 | Partial Approval | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 1/20/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/24/2023 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 1/25/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/25/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 1/25/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/3/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/3/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/6/2023 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 2/14/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/14/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/15/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/16/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/17/2023 | Conditional Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 2/17/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/3/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 3/6/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/8/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/9/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 3/13/2023 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 3/16/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/23/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 3/24/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Reinf. Concrete | 3/28/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/28/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/29/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/5/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 4/5/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/6/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/7/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/10/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/11/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/13/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 4/13/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/14/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 4/24/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 4/25/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 4/26/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/27/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 4/27/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 4/27/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/28/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 4/28/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/1/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/1/2023 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 5/1/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/2/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/2/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/2/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/3/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/3/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/4/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/5/2023 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 5/8/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/15/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/15/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/15/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 5/17/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/18/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/19/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/22/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 5/23/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/24/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/25/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/26/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/26/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/30/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/30/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 5/31/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/1/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 6/1/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/1/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 6/2/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/5/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/6/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/7/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/12/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/13/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/13/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/14/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/15/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/15/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/15/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/16/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/16/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/20/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/20/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/21/2023 | Approved | NICK LAROCCA |
| Deputy Reinf. Masonry | 6/21/2023 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 6/22/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/23/2023 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 6/23/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/26/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/26/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/27/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/27/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 6/28/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/29/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/29/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/29/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/30/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 7/6/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/7/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 7/10/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 7/12/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/12/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/12/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 7/13/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/14/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/18/2023 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 7/19/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 7/20/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 7/20/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/20/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 7/21/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/24/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/25/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 7/26/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/27/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/28/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/31/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 8/1/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/1/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/1/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/1/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 8/2/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 8/3/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/3/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/3/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 8/3/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/4/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/4/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/7/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/8/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/9/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 8/10/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 8/10/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/10/2023 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 8/11/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 8/14/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 8/15/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/15/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/15/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/16/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/17/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/25/2023 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/31/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/15/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/21/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 9/21/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/25/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/29/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/29/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 9/29/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/5/2023 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/6/2023 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/12/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/12/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 10/13/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/19/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/25/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/31/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/1/2023 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 11/2/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 11/7/2023 | Partial Approval | DERRICK SPENCER |
| Reinforced Masonry Frame | 11/8/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 11/9/2023 | Not Ready for Inspection | DAVID TSAU |
| Light Gage Steel Frame | 11/9/2023 | Partial Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 11/13/2023 | Conditional Approval | DERRICK SPENCER |
| Reinforced Masonry Frame | 11/15/2023 | Partial Approval | DERRICK SPENCER |
| Reinforced Masonry Frame | 11/20/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 11/21/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/22/2023 | Approved | DERRICK SPENCER |
| Masonry Wall/Backfill | 11/27/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 11/28/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/29/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/30/2023 | Approved | DERRICK SPENCER |
| Insulation | 12/1/2023 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 12/1/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/4/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/5/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/6/2023 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 12/7/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/13/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 12/15/2023 | Partial Inspection | DERRICK SPENCER |
| Reinforced Masonry Frame | 12/29/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/8/2024 | Partial Approval | DERRICK SPENCER |
| Reinforced Masonry Frame | 1/11/2024 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/31/2024 | Approved | DERRICK SPENCER |
| Deputy Other (see comments) | 2/6/2024 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 2/20/2024 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 3/4/2024 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 4/10/2024 | Partial Approval | DERRICK SPENCER |
| T-Bar Ceiling | 4/23/2024 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/3/2024 | Partial Approval | RICARDO ROBLES |
| Pre-Inspection | 5/3/2024 | Approved | DAVID TSAU |
| Special/Order Compliance | 5/23/2024 | Approved | DERRICK SPENCER |
| Drywall Nailing | 7/30/2024 | Approved | DERRICK SPENCER |
| Final | 7/30/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/30/2024 | Approved | DERRICK SPENCER |
| Green Building Final | 7/30/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Reinforced Masonry Frame | 7/30/2024 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 7/30/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/4/2024 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 12/5/2024 | Approved | DERRICK SPENCER |
| Final | 12/23/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 12/23/2024 | Approved | DERRICK SPENCER |
| Final | 1/6/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 1/6/2025 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 1/6/2025 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 1/8/2025 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/30/2025 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 1/30/2025 | Approved | DERRICK SPENCER |
| Final | 2/3/2025 | OK to Issue CofO | DERRICK SPENCER |
| Final | 2/11/2025 | Partial Inspection | DERRICK SPENCER |
| Special/Order Compliance | 7/15/2025 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 1/6/2026 | Approved | DERRICK SPENCER |
| Final | 2/3/2026 | Not Ready for Inspection | DERRICK SPENCER |