9785 S BELLANCA AVE 90045

Certificate Information: 9785 S BELLANCA AVE 90045

Application / Permit
21010-10000-03519
Plan Check / Job No.
B21LA13134
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
CONSTRUCTION OF 143,081 SF SPECULATIVE WAREHOUSE INCLUDES W/ OFFICE/BREAK SPACE. OFF SITE PARKING AT 5760 W ARBOR VITAE ST UNDER SEPARATE PERMIT.
Permit Issued
Issued on 11/21/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Green Plans Picked Up 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 SERGIO GUTIERREZ
Corrections Issued 9/15/2021 SERGIO GUTIERREZ
Disabled Access Plans Picked Up 9/15/2021 APPLICANT
Quality Review Completed 9/16/2021 FARUK SEZER
Building Plans Picked Up 9/20/2021 APPLICANT
Applicant returned to address corrections 1/24/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 1/26/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 2/17/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 5/13/2022 SERGIO GUTIERREZ
Plan Check Approved 11/16/2022 SERGIO GUTIERREZ
Issued 11/21/2022 APPLICANT
CofO in Progress 2/11/2025 DERRICK SPENCER
No Progress 2/14/2025 DAVID TSAU
CofO in Progress 2/14/2025 DAVID TSAU
TCO Issued (Expire Date: 08-13-2025) 2/14/2025 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 01-26-2026) 7/30/2025 HENRY BAGHDASSARIAN
CofO in Progress 2/4/2026 DERRICK SPENCER
CofO in Progress 2/13/2026 VASIL MIHALEV
Permit Finaled 3/4/2026 VASIL MIHALEV
CofO Issued 3/4/2026 VASIL MIHALEV
Permit Finaled 3/4/2026 VASIL MIHALEV

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 6/29/2022 RYAN LY
Miscellaneous Cleared 6/29/2022 RYAN LY
Green Code Cleared 6/30/2022 AARON COSTA
Low Impact Development Cleared 6/30/2022 SARAH YOUSSEF
Stormwater Pollution Mitigatn Cleared 6/30/2022 SARAH YOUSSEF
Comm Cor/Mini-Mall Cleared 7/1/2022 RYAN LY
Comm Cor/Mini-Mall Cleared 7/1/2022 RYAN LY
Prkng lot landscape/Water mgmt Cleared 7/6/2022 RYAN LY
DAS Clearance Cleared 7/20/2022 SERGIO GUTIERREZ
Fire Marshal Fire Life Safety Cleared 7/20/2022 MENOA AGHAJANI
Eng Process Fee Ord 176,300 Cleared 7/27/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 7/28/2022 CATHERINE ADROVER
Highway dedication Cleared 8/16/2022 RAYMOND MUGAMBWA
Permit Cleared 8/30/2022 CATHERINE ADROVER
Sewer availability Cleared 8/31/2022 CATHERINE ADROVER
Internal circulation Cleared 9/27/2022 PEDRO AYALA
Specific Plan Cleared 9/28/2022 PEDRO AYALA
Address approval Cleared 10/12/2022 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 11/4/2022 GILBERT URREA
Building over 36-ft Cleared 11/16/2022 CALOSHA APPROVED

Contact Information

Architect Nam,, Yong Hwan; Lic. No.: C29451 18831 BARDEEN AVENUE # 100      IRVINE, CA 92612
Contractor Millie And Severson General Contractors; Lic. No.: 99031-B P O BOX 3601      LOS ALAMITOS, CA 90720
Engineer Gerges,, Rafik; Lic. No.: S5092 1906 W GARVEY AVE STE 200      WEST COVINA, CA 91790
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/23/2022 Approved DERRICK SPENCER
Pre-Inspection 11/30/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 12/8/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 12/8/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 12/9/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 1/3/2023 Partial Approval DERRICK SPENCER
SWPPP-Const. Storm Water 1/4/2023 Completed DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 1/10/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 1/20/2023 Conditional Approval DERRICK SPENCER
Green Building Rough 1/20/2023 Approved DERRICK SPENCER
Reinforced Concrete Frame 1/20/2023 Partial Approval DERRICK SPENCER
Verify Sprinkler Sign Off 1/20/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 1/24/2023 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 1/25/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 1/25/2023 Partial Approval DERRICK SPENCER
Pre-Inspection 1/25/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 2/3/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 2/3/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/6/2023 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/14/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 2/14/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/15/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 2/16/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 2/17/2023 Conditional Approval DERRICK SPENCER
Reinforced Concrete Frame 2/17/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/3/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 3/6/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/8/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/9/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 3/13/2023 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/16/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/23/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 3/24/2023 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 3/28/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/28/2023 Conditional Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/29/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/5/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 4/5/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/6/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/7/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/10/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 4/10/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/11/2023 Conditional Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/13/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 4/13/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/14/2023 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 4/24/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 4/25/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 4/26/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 4/27/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 4/27/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 4/27/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/28/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 4/28/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 5/1/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/1/2023 Approved DERRICK SPENCER
Structural Steel Frame 5/1/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/2/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/2/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 5/2/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/3/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/3/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/4/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/5/2023 Approved NICK LAROCCA
Deputy Steel/Welding 5/8/2023 Conditional Approval DERRICK SPENCER
Deputy Drilled-In Anchors 5/9/2023 Conditional Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/15/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/15/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 5/15/2023 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 5/17/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/18/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/19/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/22/2023 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 5/23/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/24/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/25/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/26/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 5/26/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/30/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/30/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 5/31/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/1/2023 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 6/1/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 6/1/2023 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 6/2/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/5/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/6/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 6/6/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/7/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/12/2023 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/13/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/13/2023 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/14/2023 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/15/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/15/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 6/15/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 6/16/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/16/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/20/2023 Approved DERRICK SPENCER
Deputy Reinf. Masonry 6/20/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/21/2023 Approved NICK LAROCCA
Deputy Reinf. Masonry 6/21/2023 Approved NICK LAROCCA
Deputy Reinf. Concrete 6/22/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/23/2023 Approved NICK LAROCCA
Footing/Foundation/Slab 6/23/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/26/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/26/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/27/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/27/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 6/28/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/29/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 6/29/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 6/29/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/30/2023 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 7/6/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/7/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 7/10/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 7/12/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/12/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 7/12/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 7/13/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/14/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/18/2023 Approved NICK LAROCCA
Deputy Steel/Welding 7/19/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 7/20/2023 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 7/20/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 7/20/2023 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 7/21/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/24/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/25/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 7/25/2023 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 7/26/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/27/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/28/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 7/31/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 8/1/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/1/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/1/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/1/2023 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 8/2/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 8/3/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/3/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/3/2023 Conditional Approval DERRICK SPENCER
Deputy Steel/Welding 8/3/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/4/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/4/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/7/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/8/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/9/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 8/10/2023 Approved DERRICK SPENCER
Deputy Reinf. Masonry 8/10/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/10/2023 Approved DERRICK SPENCER
Deputy Steel/Welding 8/11/2023 Approved DERRICK SPENCER
Deputy Reinf. Masonry 8/14/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 8/15/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/15/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/15/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/16/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/17/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/25/2023 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 8/29/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 8/31/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/15/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/21/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 9/21/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 9/25/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/29/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/29/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 9/29/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 10/5/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 10/6/2023 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 10/12/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 10/12/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 10/13/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 10/19/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 10/25/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 10/31/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 11/1/2023 Approved DERRICK SPENCER
Reinforced Masonry Frame 11/2/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 11/7/2023 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 11/8/2023 Partial Approval DERRICK SPENCER
Drywall Nailing 11/9/2023 Not Ready for Inspection DAVID TSAU
Light Gage Steel Frame 11/9/2023 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 11/13/2023 Conditional Approval DERRICK SPENCER
Reinforced Masonry Frame 11/15/2023 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 11/20/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 11/21/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 11/22/2023 Approved DERRICK SPENCER
Masonry Wall/Backfill 11/27/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 11/28/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 11/29/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 11/30/2023 Approved DERRICK SPENCER
Insulation 12/1/2023 Approved DERRICK SPENCER
Reinforced Masonry Frame 12/1/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 12/4/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 12/5/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 12/6/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 12/7/2023 Approved DERRICK SPENCER
Footing/Foundation/Slab 12/13/2023 Partial Approval DERRICK SPENCER
Drywall Nailing 12/15/2023 Partial Inspection DERRICK SPENCER
Reinforced Masonry Frame 12/29/2023 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 1/8/2024 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 1/11/2024 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 1/31/2024 Approved DERRICK SPENCER
Deputy Other (see comments) 2/6/2024 Approved DERRICK SPENCER
Light Gage Steel Frame 2/20/2024 Partial Approval DERRICK SPENCER
Drywall Nailing 3/4/2024 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/10/2024 Partial Approval DERRICK SPENCER
T-Bar Ceiling 4/23/2024 Approved DERRICK SPENCER
Footing/Foundation/Slab 5/3/2024 Partial Approval RICARDO ROBLES
Pre-Inspection 5/3/2024 Approved DAVID TSAU
Special/Order Compliance 5/23/2024 Approved DERRICK SPENCER
Drywall Nailing 7/30/2024 Approved DERRICK SPENCER
Final 7/30/2024 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 7/30/2024 Approved DERRICK SPENCER
Green Building Final 7/30/2024 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 7/30/2024 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 7/30/2024 SGSOV Approved DERRICK SPENCER
Smoke Detectors 7/30/2024 Approved DERRICK SPENCER
Pre-Inspection 12/4/2024 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 12/5/2024 Approved DERRICK SPENCER
Final 12/23/2024 Not Ready for Inspection DERRICK SPENCER
Green Building Final 12/23/2024 Approved DERRICK SPENCER
Final 1/6/2025 Not Ready for Inspection DERRICK SPENCER
Pre-Inspection 1/6/2025 Approved DERRICK SPENCER
Special/Order Compliance 1/6/2025 Approved DERRICK SPENCER
Deputy Steel/Welding 1/8/2025 Approved DERRICK SPENCER
Pre-Inspection 1/30/2025 Approved DERRICK SPENCER
Special/Order Compliance 1/30/2025 Approved DERRICK SPENCER
Final 2/3/2025 OK to Issue CofO DERRICK SPENCER
Final 2/11/2025 Partial Inspection DERRICK SPENCER
Special/Order Compliance 7/15/2025 Approved DERRICK SPENCER
Special/Order Compliance 1/6/2026 Approved DERRICK SPENCER
Final 2/3/2026 Not Ready for Inspection DERRICK SPENCER