4670 E PAULA ST 90032
Certificate Information: 4670 E PAULA ST 90032
- Application / Permit
- 21010-10000-03516
- Plan Check / Job No.
- B21LA13122
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU PER LAMC 12.22A.33 (c) - (d) WITH ATTACHED 3-CAR GARAGES
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/26/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/1/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/13/2021 | APPLICANT |
| Applicant returned to address corrections | 2/1/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/28/2023 | MAHNAZ NOURHASHEMI |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 2/9/2026 | LILIANA PORTILLO |
| Permit Finaled | 2/10/2026 | DEROLD HAUFF |
| CofO Issued | 2/10/2026 | DEROLD HAUFF |
| Permit Finaled | 2/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 2/1/2022 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 2/1/2022 | MAHNAZ NOURHASHEMI |
| Address approval | Cleared | 6/28/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 7/5/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 2/8/2023 | DEBORA LEITE |
| Hydrant and Access approval | Cleared | 3/7/2023 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 4/20/2023 | STEVE MELGAR |
Contact Information
| Contractor | David General Building Construction Inc; Lic. No.: 768772-B | 2929 W VALLEY BLVD ALHAMBRA, CA 91803 |
| Engineer | Liu,, Wen-Young; Lic. No.: C70729 | 448 LINWOOD AVE MONROVIA, CA 91016 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/22/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/28/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 11/6/2024 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Approved | LILIANA PORTILLO |
| Gas Test | 11/7/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/7/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 11/7/2024 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/12/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/12/2024 | Approved | LILIANA PORTILLO |
| Insulation | 11/19/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 12/4/2024 | Approved | JOSH MEISTER |
| Green Building Rough | 12/4/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 12/4/2024 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/5/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 12/12/2024 | Approved | LILIANA PORTILLO |
| Sewer | 1/17/2025 | Approved | LILIANA PORTILLO |
| Final | 2/28/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/28/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 2/28/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 2/28/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/22/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/22/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/12/2026 | Approved | LILIANA PORTILLO |
| Final | 1/12/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/12/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 1/12/2026 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 1/12/2026 | Approved | LILIANA PORTILLO |
| Final | 2/6/2026 | OK to Issue CofO | LILIANA PORTILLO |