1666 N BROAD AVE 90744
Certificate Information: 1666 N BROAD AVE 90744
- Application / Permit
- 21010-10000-03513
- Plan Check / Job No.
- B21LA13089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW ATTACHED ACCESSORY DWELLING UNIT PER ORDINANCE The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- Issued on 1/20/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2021 | DANIEL YIP |
| Plans on Hold | 7/20/2021 | MONICA RAMIREZ |
| Hold Released | 7/28/2021 | MONICA RAMIREZ |
| Corrections Issued | 7/28/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/8/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/17/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/21/2021 | DANIEL YIP |
| Plan Check Approved | 1/19/2022 | DANIEL YIP |
| Issued | 1/20/2022 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 7/27/2021 | JASON SHEETS |
| Hold | Cleared | 7/27/2021 | JASON SHEETS |
| Address approval | Cleared | 8/17/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/17/2021 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 1/10/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 2/2/2022 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 2/2/2022 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 2/2/2022 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/14/2022 | Conditional Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 2/23/2022 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 2/28/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/19/2022 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 4/19/2022 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/19/2022 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/22/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/29/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 7/7/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 7/7/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/1/2022 | Approved | EUGENE CASSIDY |
| Final | 8/1/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/1/2022 | Approved | EUGENE CASSIDY |
| METHANE-Final | 8/1/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 8/1/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 8/1/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/8/2022 | Approved | EUGENE CASSIDY |
| Final | 8/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 8/8/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/8/2022 | Approved | EUGENE CASSIDY |
| Final | 10/18/2024 | Corrections Issued | EUGENE CASSIDY |
| Final | 4/23/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 4/24/2025 | Corrections Issued | EUGENE CASSIDY |