879 1/2 N HYPERION AVE 90029
Certificate Information: 879 1/2 N HYPERION AVE 90029
- Application / Permit
- 21010-10000-03506
- Plan Check / Job No.
- B21LA13084
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *ePLAN* CONVERSION OF STORAGE IN (E) DUPLEX TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | LAMAR DAVIS |
| Corrections Issued | 8/9/2021 | LAMAR DAVIS |
| Quality Review Completed | 8/10/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 9/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 9/15/2021 | LAMAR DAVIS |
| Plan Check Approved | 2/9/2022 | LAMAR DAVIS |
| Issued | 12/13/2022 | APPLICANT |
| CofO in Progress | 9/23/2024 | FREDDIE RIVERA |
| CofO in Progress | 10/11/2024 | FREDDIE RIVERA |
| CofO in Progress | 1/31/2025 | FREDDIE RIVERA |
| No Progress | 1/31/2025 | OSVALDO PARAMO |
| Permit Finaled | 2/26/2025 | DEROLD HAUFF |
| CofO Issued | 2/26/2025 | DEROLD HAUFF |
| Permit Finaled | 2/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 8/13/2021 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 8/13/2021 | RUBEN VASQUEZ |
| Address approval | Cleared | 8/13/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/13/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 8/24/2021 | PATRICK MISCHLICH |
| Construction near power lines | Cleared | 1/25/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Dischman Construction Management Inc; Lic. No.: 1055267-B | 3675 NEW HAVEN RD PASADENA, CA 91107 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/18/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/18/2023 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/11/2023 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/11/2023 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 10/11/2023 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 10/11/2023 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 10/18/2023 | Approved | FREDDIE RIVERA |
| Shower Pan | 11/7/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/13/2023 | Approved | FREDDIE RIVERA |
| Final | 3/15/2024 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 3/15/2024 | Approved | FREDDIE RIVERA |
| Final | 6/17/2024 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/17/2024 | SGSOV Approved | FREDDIE RIVERA |
| Final | 8/5/2024 | Partial Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 8/5/2024 | Partial Inspection | ANTHONY RAMOS |
| Final | 9/9/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 9/23/2024 | OK to Issue CofO | FREDDIE RIVERA |
| Special/Order Compliance | 10/11/2024 | Corrections Issued | FREDDIE RIVERA |