1448 W 83RD ST 90047
Certificate Information: 1448 W 83RD ST 90047
- Application / Permit
- 21010-10000-03483
- Plan Check / Job No.
- B21LA12973
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE (FRONT BUILDING). 1 OF 2
- Permit Issued
- Issued on 2/4/2022
- Issuing Office
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | VARAND SARKISIAN |
| Corrections Issued | 8/9/2021 | VARAND SARKISIAN |
| Quality Review Completed | 8/11/2021 | HANS SANTIAGO |
| Plan Check Approved | 9/30/2021 | VARAND SARKISIAN |
| Issued | 2/4/2022 | APPLICANT |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| CofO in Progress | 8/30/2022 | LILIANA PORTILLO |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/30/2021 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 8/31/2021 | DENZEL HENDERSON |
| Trees in Parkway | Cleared | 9/2/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/8/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/24/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/28/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/3/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/21/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 4/18/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/4/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 5/4/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/5/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 5/5/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/5/2022 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 5/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 5/5/2022 | Approved | LILIANA PORTILLO |
| Insulation | 5/11/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/17/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/17/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 6/21/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/22/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/27/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/17/2022 | Approved | LILIANA PORTILLO |
| Final | 8/17/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/17/2022 | Approved | LILIANA PORTILLO |
| Green Building Final | 8/17/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 8/17/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/17/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 8/17/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 8/17/2022 | Approved | LILIANA PORTILLO |
| Final | 8/23/2022 | OK to Issue CofO | LILIANA PORTILLO |
| PLUMBING-Final | 8/23/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/23/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/26/2022 | Approved | LILIANA PORTILLO |