619 W 83RD ST 90044

Certificate Information: 619 W 83RD ST 90044

Application / Permit
21010-10000-03481
Plan Check / Job No.
B21LA12966
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY (45.5' X 26') SFD (1145 SF) WITH ATTACHED 4-CAR GARAGE (863 SF) AT REAR. 2 OF 2
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 VIVIAN LAO
Corrections Issued 8/11/2021 VIVIAN LAO
Quality Review Completed 8/24/2021 MICHAEL PEREZ
Applicant returned to address corrections 11/3/2021 VIVIAN LAO
Plan Check Approved 11/15/2021 VIVIAN LAO
Issued 5/2/2022 APPLICANT
Building Plans Picked Up 5/3/2022 APPLICANT
CofO in Progress 12/21/2022 LILIANA PORTILLO
Permit Finaled 1/4/2023 DEROLD HAUFF
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/1/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/1/2021 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 9/3/2021 DENZEL HENDERSON
Address approval Cleared 9/10/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/22/2021 RENZ SORIANO
Hydrant and Access approval Cleared 9/25/2021 ROBERT DUFF
Sewer availability Cleared 10/20/2021 RENZ SORIANO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2022 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 7/8/2022 Approved LILIANA PORTILLO
Underground Mechanical 7/8/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 7/14/2022 Approved LILIANA PORTILLO
Underground Mechanical 7/14/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 7/15/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/19/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 7/19/2022 Approved LILIANA PORTILLO
Green Building Rough 7/19/2022 Approved LILIANA PORTILLO
Insulation 7/22/2022 Partial Inspection ANTHONY EGSON
Special/Order Compliance 8/15/2022 Not Ready for Inspection LILIANA PORTILLO
Insulation 8/26/2022 Approved LILIANA PORTILLO
Drywall Nailing 9/6/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 9/6/2022 Not Ready for Inspection LILIANA PORTILLO
Special/Order Compliance 9/6/2022 Approved LILIANA PORTILLO
Underground Mechanical 10/31/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/6/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 12/13/2022 Corrections Issued LILIANA PORTILLO
Final 12/13/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 12/13/2022 Approved LILIANA PORTILLO
Green Building Final 12/13/2022 Approved LILIANA PORTILLO
HVAC-Final 12/13/2022 Approved LILIANA PORTILLO
PLUMBING-Final 12/13/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 12/13/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/13/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/14/2022 Approved LILIANA PORTILLO
Final 12/19/2022 Conditional Approval LILIANA PORTILLO
Service/Power Release 12/19/2022 Approved LILIANA PORTILLO
Final 12/20/2022 Conditional Approval LILIANA PORTILLO
Service/Power Release 12/20/2022 Approved LILIANA PORTILLO