231-233 E 106TH ST 90003

Certificate Information: 231-233 E 106TH ST 90003

Application / Permit
21010-10000-03476
Plan Check / Job No.
B21LA12947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
Permit Issued
Issued on 12/21/2021
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 MAHNAZ NOURHASHEMI
Corrections Issued 8/10/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 8/18/2021 JASON HEALEY
Building Plans Picked Up 8/23/2021 APPLICANT
Plan Check Approved 10/28/2021 MAHNAZ NOURHASHEMI
Issued 12/21/2021 APPLICANT
CofO in Progress 6/29/2022 ALIZAH MAYAGOITIA
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 8/30/2021 ANACANY HURTADO
Address approval Cleared 9/1/2021 JEANIE LAM
Permit Cleared 9/1/2021 JEANIE LAM
Trees in Parkway Cleared 9/2/2021 JOHN KIM
Sewer availability Cleared 9/8/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/10/2021 JEANIE LAM
Low Impact Development Cleared 9/22/2021 MARCO SANCHEZ
Hydrant and Access approval Cleared 10/14/2021 ROBERT DUFF
Roof/Waste drainage to street Cleared 10/22/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/4/2022 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Not Ready for Inspection JOHN KLARIN
Underground Mechanical 2/4/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval JOSEPH MCGARRY
Insulation 2/7/2022 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 3/25/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 3/25/2022 Approved JOHN KLARIN
Green Building Rough 3/25/2022 Approved JOHN KLARIN
HVAC-Rough 3/25/2022 Approved JOHN KLARIN
PLUMBING-Rough 3/25/2022 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 3/25/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/25/2022 Approved JOHN KLARIN
Insulation 3/29/2022 Approved JOHN KLARIN
Drywall Nailing 4/18/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 4/18/2022 Approved JOHN KLARIN
ELECTRICAL-Final 6/6/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/24/2022 Approved ALIZAH MAYAGOITIA
Final 6/24/2022 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 6/24/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/24/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/24/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 6/24/2022 Approved ALIZAH MAYAGOITIA
Smoke Detectors 6/24/2022 Approved ALIZAH MAYAGOITIA
Final 6/29/2022 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 6/29/2022 Approved ALIZAH MAYAGOITIA