633 E 23RD ST 90011
Certificate Information: 633 E 23RD ST 90011
- Application / Permit
- 21010-10000-03475
- Plan Check / Job No.
- B21LA12939
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU WITH ATTACHED GARAGE PER 12.22 A33 C & D (REAR)
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | STARR CHEN |
| Corrections Issued | 8/7/2021 | STARR CHEN |
| Quality Review Completed | 12/9/2021 | WING SUEN |
| Applicant returned to address corrections | 12/10/2021 | STARR CHEN |
| Plan Check Approved | 12/13/2021 | STARR CHEN |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/9/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
| CofO Issued | 12/31/2022 | DEROLD HAUFF |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/31/2021 | DENZEL HENDERSON |
| Frnt yard landscape/Water mgmt | Cleared | 8/31/2021 | DENZEL HENDERSON |
| Address approval | Cleared | 9/3/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 9/17/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/19/2021 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | CELINA MORENO |
| Highway dedication | Cleared | 12/8/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS PARK |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/3/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/15/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/15/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/18/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/18/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 7/18/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 7/18/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 7/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 7/25/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| Sewer | 8/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/15/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/26/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Final | 10/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/26/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/31/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/22/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/22/2022 | Approved | ALEJANDRO DE ARTOLA |