1070-1072 W 62ND ST 90044

Certificate Information: 1070-1072 W 62ND ST 90044

Application / Permit
21010-10000-03472
Plan Check / Job No.
B21LA12937
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR.
Permit Issued
Issued on 12/23/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 DANIEL YIP
Corrections Issued 8/9/2021 DANIEL YIP
Quality Review Completed 8/17/2021 JASON HEALEY
Building Plans Picked Up 9/22/2021 APPLICANT
Plan Check Approved 10/1/2021 DANIEL YIP
Issued 12/23/2021 APPLICANT
CofO in Progress 7/29/2022 JOAQUIN GREENOUGH
CofO in Progress 7/29/2022 JOAQUIN GREENOUGH
Permit Finaled 8/2/2022 DEROLD HAUFF
CofO Issued 8/2/2022 DEROLD HAUFF
Permit Finaled 8/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2021 WALLIE JONG
Permit Cleared 8/26/2021 WALLIE JONG
Trees in Parkway Cleared 8/26/2021 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 8/30/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/12/2021 ROBERT DUFF
Low Impact Development Cleared 9/21/2021 TA ANH
Roof/Waste drainage to street Cleared 9/23/2021 CELINA MORENO
Sewer availability Cleared 9/30/2021 WALLIE JONG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/28/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 2/7/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 2/8/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Conditional Approval JOAQUIN GREENOUGH
HVAC-Rough 4/15/2022 Approved STUART CHAPMAN
PLUMBING-Rough 4/15/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 4/18/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/18/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 4/18/2022 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 4/18/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/19/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/19/2022 Approved JOAQUIN GREENOUGH
Insulation 4/19/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 4/21/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 5/12/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 5/12/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 7/14/2022 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Final 7/27/2022 Approved JOAQUIN GREENOUGH
Final 7/27/2022 OK to Issue CofO JOAQUIN GREENOUGH
Green Building Final 7/27/2022 Approved JOAQUIN GREENOUGH
HVAC-Final 7/27/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Final 7/27/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 7/27/2022 Approved JOAQUIN GREENOUGH
Smoke Detectors 7/27/2022 Approved JOAQUIN GREENOUGH
Final 7/29/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 7/29/2022 Approved JOAQUIN GREENOUGH