834-836 E 85TH ST 90001

Certificate Information: 834-836 E 85TH ST 90001

Application / Permit
21010-10000-03470
Plan Check / Job No.
B21LA12934
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR.
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 6/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 SERGIO GUTIERREZ
Corrections Issued 8/4/2021 SERGIO GUTIERREZ
Quality Review Completed 8/12/2021 ALLEN MANALANSAN
Plan Check Approved 10/29/2021 SERGIO GUTIERREZ
Issued 12/10/2021 APPLICANT
Building Plans Picked Up 12/13/2021 APPLICANT
CofO in Progress 6/9/2022 ALEJANDRO DE ARTOLA
Permit Finaled 6/22/2022 DEROLD HAUFF
CofO Issued 6/22/2022 DEROLD HAUFF
Permit Finaled 6/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/31/2021 CECILIO NAVARRO
Frnt yard landscape/Water mgmt Cleared 8/31/2021 DENZEL HENDERSON
Highway dedication Cleared 8/31/2021 CECILIO NAVARRO
Sewer availability Cleared 8/31/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 9/8/2021 ROBERT DUFF
Permit Cleared 9/14/2021 CECILIO NAVARRO
Low Impact Development Cleared 10/7/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/8/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/10/2022 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/11/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 1/12/2022 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/12/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/18/2022 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/18/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Partial Approval JOAQUIN GREENOUGH
Special/Order Compliance 2/14/2022 Partial Inspection LILIANA PORTILLO
HVAC-Rough 3/10/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 3/10/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/11/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 3/11/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/14/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/14/2022 Approved ALEJANDRO DE ARTOLA
Insulation 3/14/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 4/5/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/5/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/20/2022 Partial Approval LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 6/7/2022 Approved ALEJANDRO DE ARTOLA
Final 6/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/7/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 6/7/2022 Approved ALEJANDRO DE ARTOLA
Final 6/8/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/8/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 6/8/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/8/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/8/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 6/8/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/8/2022 Approved ALEJANDRO DE ARTOLA