1546 W AVERILL PARK DR 90732
Certificate Information: 1546 W AVERILL PARK DR 90732
- Application / Permit
- 21010-10000-03462
- Plan Check / Job No.
- B21LA12910
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- New 14'-3"x24'- 0" one story, detached recreation room with a pool bath- no kitchen.
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/27/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | KESETE HAREGOT |
| Corrections Issued | 8/6/2021 | KESETE HAREGOT |
| Quality Review Completed | 8/18/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 3/14/2022 | KESETE HAREGOT |
| Plan Check Approved | 3/18/2022 | KESETE HAREGOT |
| Issued | 5/27/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2021 | ERIK BEASLEY |
| Address approval | Cleared | 10/21/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/21/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/21/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/21/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/21/2021 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 10/21/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/8/2021 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 1/12/2022 | KESETE HAREGOT |
| Grading Pre-Inspection | Cleared | 1/12/2022 | KESETE HAREGOT |
| Green Code | Cleared | 1/12/2022 | KESETE HAREGOT |
| Low Impact Development | Cleared | 2/15/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/17/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/12/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/1/2022 | Corrections Issued | ANSON MAGLASANG |
| Deputy Drilled-In Anchors | 8/2/2022 | Conditional Approval | ANSON MAGLASANG |
| Deputy Reinf. Concrete | 8/9/2022 | Conditional Approval | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/9/2022 | Conditional Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 9/27/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Wood Frame | 9/27/2022 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | ANSON MAGLASANG |
| Structural Steel Frame | 10/5/2022 | Conditional Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 12/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 12/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 12/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Rough | 12/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 12/8/2022 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 12/8/2022 | Partial Inspection | JOHN KLARIN |
| Wood Frame | 12/8/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 12/12/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 12/12/2022 | Approved | JOHN KLARIN |
| Insulation | 12/12/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 12/16/2022 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 12/22/2022 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Final | 7/5/2023 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/6/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/6/2023 | Approved | JOHN KLARIN |
| Green Building Final | 7/6/2023 | Corrections Issued | JOHN KLARIN |
| Pre-Inspection | 7/6/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/6/2023 | Approved | JOHN KLARIN |
| Special/Order Compliance | 7/6/2023 | Corrections Issued | JOHN KLARIN |
| Special/Order Compliance | 2/6/2025 | Corrections Issued | JOSEPH MCGARRY |