18801 W EDLEEN DR 91356
Certificate Information: 18801 W EDLEEN DR 91356
- Application / Permit
- 21010-10000-03452
- Plan Check / Job No.
- B21LA12907
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY S.F.D. WITH ATTACHED GARAGE AND BASEMENT AND ROOF DECK WITH DECK ON CAISONS. 1 OF 4
- Permit Issued
- Issued on 10/24/2022
- Issuing Office
- Valley
- Current Status
- Issued on 10/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 9/22/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/27/2021 | FARUK SEZER |
| Building Plans Picked Up | 10/5/2021 | APPLICANT |
| Applicant returned to address corrections | 2/10/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 9/1/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/21/2022 | SERGIO GUTIERREZ |
| Issued | 10/24/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
| Permit | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 9/23/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/29/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 11/19/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 1/6/2022 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 2/3/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/31/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/3/2022 | JOSE DUARTE-DIAZ |
| GPI Written Notices | Cleared | 9/1/2022 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 9/1/2022 | SERGIO GUTIERREZ |
| Stormwater Pollution Mitigatn | Cleared | 9/1/2022 | MARTIN FRAGOSO |
| Miscellaneous | Cleared | 10/21/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 1722 CEDAR STREET APT G ALHAMBRA, CA 91801 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 11/14/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Grading | 11/15/2022 | Corrections Issued | DAVID SANDOVAL |
| Deputy Grading | 11/16/2022 | Approved | DAVID SANDOVAL |
| Deputy Grading | 11/17/2022 | Approved | DAVID SANDOVAL |
| Deputy Grading | 11/18/2022 | Approved | DAVID SANDOVAL |
| Deputy Grading | 11/29/2022 | Approved | DAVID SANDOVAL |
| Deputy Grading | 6/15/2023 | Partial Approval | SEAN WIRCH |
| Deputy Grading | 6/16/2023 | Approved | SEAN WIRCH |
| Deputy Grading | 6/21/2023 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 6/28/2023 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 6/29/2023 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 6/30/2023 | Approved | SEAN HAUPT |
| Reinforced Concrete Frame | 7/26/2023 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/27/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 8/2/2023 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/9/2023 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 8/10/2023 | Approved | JEFFREY PARD |
| Reinforced Concrete Frame | 8/17/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 10/6/2023 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/10/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 10/24/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/24/2023 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 10/24/2023 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/26/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 11/6/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 11/6/2023 | Corrections Issued | SEAN HAUPT |
| Deputy Steel/Welding | 11/13/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 12/1/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Corrections Issued | SEAN HAUPT |
| Pre-Inspection | 2/9/2024 | Partial Approval | SEAN HAUPT |
| Deputy Wood Construction | 2/12/2024 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/21/2024 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 2/21/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 2/21/2024 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 2/21/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 2/21/2024 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/21/2024 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/26/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 2/26/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/26/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | JOHN KIDWELL |
| Insulation | 3/4/2024 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 3/18/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/2/2024 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | JOHN KIDWELL |
| Sewer | 9/30/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 4/2/2025 | Corrections Issued | JON MCHUGH |
| Gas Test | 4/8/2025 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 4/17/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 7/8/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 7/15/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/1/2025 | Conditional Approval | JOHN KIDWELL |
| Service/Power Release | 8/1/2025 | Approved | JOHN KIDWELL |