5201 N FULTON AVE 91401
Certificate Information: 5201 N FULTON AVE 91401
- Application / Permit
- 21010-10000-03450
- Plan Check / Job No.
- B21LA12905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD WITH ATTACHED 2-CAR GARAGE. *INSTRUCTED BY TEO DIAZ TO ENFORCE ADDRESS ON APPLICATION ON 7/9/2021 AT 10:45AM*
- Permit Issued
- Issued on 1/21/2022
- Issuing Office
- Current Status
- CofO Issued on 5/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/4/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/12/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Applicant returned to address corrections | 12/23/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 1/20/2022 | MAHNAZ NOURHASHEMI |
| Issued | 1/21/2022 | APPLICANT |
| CofO in Progress | 5/4/2023 | MISAEL ESPARZA |
| CofO Issued | 5/8/2023 | MICHAEL SMITH |
| Permit Finaled | 5/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/2/2021 | LEE GUILBEAUX |
| Highway dedication | Cleared | 9/2/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/2/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/7/2021 | LEE GUILBEAUX |
| Tract Map conditions | Cleared | 9/27/2021 | RICHARD REASER |
| Trees in Parkway | Cleared | 10/13/2021 | JOEL HERNANDEZ |
| Low Impact Development | Cleared | 11/3/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/10/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 12/9/2021 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/9/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Approved | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 4/13/2022 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 4/14/2022 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 4/14/2022 | Not Ready for Inspection | CALEB MEISTER |
| Deputy Wood Construction | 5/3/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 5/20/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 6/1/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 6/1/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/21/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Partial Approval | CALEB MEISTER |
| HVAC-Rough | 6/21/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 6/21/2022 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/24/2022 | No Access for Inspection | CALEB MEISTER |
| Green Building Rough | 6/24/2022 | No Access for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 6/24/2022 | No Access for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 7/15/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/15/2022 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 7/15/2022 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 7/15/2022 | Approved | MISAEL ESPARZA |
| Insulation | 7/27/2022 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 8/4/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/24/2022 | Approved | MISAEL ESPARZA |
| Sewer | 12/15/2022 | Partial Approval | MISAEL ESPARZA |
| Gas Test | 12/21/2022 | Approved | MISAEL ESPARZA |
| Sewer | 12/21/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/31/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 3/31/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 3/31/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 3/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 3/31/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 4/10/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 4/10/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 4/10/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 4/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 4/10/2023 | Approved | MISAEL ESPARZA |
| Final | 5/3/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 5/3/2023 | Approved | MISAEL ESPARZA |