5201 N FULTON AVE 91401

Certificate Information: 5201 N FULTON AVE 91401

Application / Permit
21010-10000-03450
Plan Check / Job No.
B21LA12905
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH ATTACHED 2-CAR GARAGE. *INSTRUCTED BY TEO DIAZ TO ENFORCE ADDRESS ON APPLICATION ON 7/9/2021 AT 10:45AM*
Permit Issued
Issued on 1/21/2022
Issuing Office
Current Status
CofO Issued on 5/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 MAHNAZ NOURHASHEMI
Corrections Issued 8/4/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 8/12/2021 ALLEN MANALANSAN
Building Plans Picked Up 8/17/2021 APPLICANT
Applicant returned to address corrections 12/23/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 1/20/2022 MAHNAZ NOURHASHEMI
Issued 1/21/2022 APPLICANT
CofO in Progress 5/4/2023 MISAEL ESPARZA
CofO Issued 5/8/2023 MICHAEL SMITH
Permit Finaled 5/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/2/2021 LEE GUILBEAUX
Highway dedication Cleared 9/2/2021 LEE GUILBEAUX
Sewer availability Cleared 9/2/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/7/2021 LEE GUILBEAUX
Sewer availability Cleared 9/7/2021 LEE GUILBEAUX
Tract Map conditions Cleared 9/27/2021 RICHARD REASER
Trees in Parkway Cleared 10/13/2021 JOEL HERNANDEZ
Low Impact Development Cleared 11/3/2021 TA ANH
Roof/Waste drainage to street Cleared 11/10/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/9/2021 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/9/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/23/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/25/2022 Approved MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 4/13/2022 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 4/14/2022 Not Ready for Inspection CALEB MEISTER
Green Building Rough 4/14/2022 Not Ready for Inspection CALEB MEISTER
Verify Sprinkler Sign Off 4/14/2022 Not Ready for Inspection CALEB MEISTER
Deputy Wood Construction 5/3/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Corrections Issued MISAEL ESPARZA
Pre-Inspection 5/20/2022 Approved MISAEL ESPARZA
HVAC-Rough 6/1/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/1/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 6/21/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval CALEB MEISTER
HVAC-Rough 6/21/2022 Approved CALEB MEISTER
PLUMBING-Rough 6/21/2022 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 6/24/2022 No Access for Inspection CALEB MEISTER
Green Building Rough 6/24/2022 No Access for Inspection CALEB MEISTER
Verify Sprinkler Sign Off 6/24/2022 No Access for Inspection CALEB MEISTER
BUILDING-Rough-Frame 7/15/2022 Approved MISAEL ESPARZA
Green Building Rough 7/15/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/15/2022 Partial Approval MISAEL ESPARZA
Shower Pan 7/15/2022 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 7/15/2022 Approved MISAEL ESPARZA
Insulation 7/27/2022 Conditional Approval MISAEL ESPARZA
Drywall Nailing 8/4/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 8/4/2022 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 8/24/2022 Approved MISAEL ESPARZA
Sewer 12/15/2022 Partial Approval MISAEL ESPARZA
Gas Test 12/21/2022 Approved MISAEL ESPARZA
Sewer 12/21/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 3/31/2023 Corrections Issued MISAEL ESPARZA
Final 3/31/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/31/2023 Approved MISAEL ESPARZA
Green Building Final 3/31/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 3/31/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 3/31/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 3/31/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 3/31/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 4/10/2023 Not Ready for Inspection MISAEL ESPARZA
Final 4/10/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 4/10/2023 Approved MISAEL ESPARZA
HVAC-Final 4/10/2023 Approved MISAEL ESPARZA
PLUMBING-Final 4/10/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 4/10/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 4/10/2023 Approved MISAEL ESPARZA
Final 5/3/2023 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 5/3/2023 Approved MISAEL ESPARZA