6250 N LINDLEY AVE 91316

Certificate Information: 6250 N LINDLEY AVE 91316

Application / Permit
21010-10000-03435
Plan Check / Job No.
B21LA12843
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 LAMAR DAVIS
Corrections Issued 8/3/2021 LAMAR DAVIS
Quality Review Completed 8/11/2021 KEN GILL
Building Plans Picked Up 8/13/2021 APPLICANT
Plan Check Approved 7/27/2022 LAMAR DAVIS
Issued 12/8/2023 APPLICANT
CofO in Progress 2/4/2026 JON MCHUGH
No Progress 4/2/2026 JON MCHUGH
CofO in Progress 4/2/2026 JON MCHUGH
CofO in Progress 5/6/2026 JON MCHUGH
CofO in Progress 5/11/2026 JOHN JANSON
Permit Finaled 5/12/2026 JOHN JANSON
CofO Issued 5/12/2026 JOHN JANSON
Permit Finaled 5/12/2026 JOHN JANSON

Permit Application Clearance Information

"T" removal Cleared 12/7/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/7/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/7/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/7/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/7/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/7/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/7/2021 MIGUEL GAMBOA
ZA Case Cleared 12/7/2021 MIGUEL GAMBOA
ZA Case Cleared 12/7/2021 MIGUEL GAMBOA
Address approval Cleared 12/8/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/8/2021 CARLOS AGUILERA
Permit Cleared 12/8/2021 CARLOS AGUILERA
Sewer availability Cleared 12/8/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 12/13/2021 JOHN CONNEALLY
ZI Cleared 1/24/2022 MIGUEL GAMBOA
Low Impact Development Cleared 4/26/2022 NICK RAYGOZA
Trees in Parkway Cleared 6/17/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 7/19/2022 CARLOS AGUILERA
Miscellaneous Cleared 7/27/2022 LAMAR DAVIS
Miscellaneous Cleared 7/27/2022 LAMAR DAVIS

Contact Information

Contractor S A B D Investments Inc; Lic. No.: 1029441-B 445 N FLORENCE STREET      BURBANK, CA 91505
Engineer Casillas,, Rafael Ortega; Lic. No.: C68234 1937 S BRADSHAWE AVE      MONTEREY PARK, CA 91754

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/6/2024 Corrections Issued JON MCHUGH
Underground Mechanical 3/7/2024 Corrections Issued JEFFREY PARD
Underground Mechanical 3/11/2024 Not Ready for Inspection JON MCHUGH
Underground Mechanical 3/13/2024 Partial Approval JON MCHUGH
Footing/Foundation/Slab 3/19/2024 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 3/21/2024 Approved JON MCHUGH
Deputy Drilled-In Anchors 5/2/2024 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Corrections Issued JON MCHUGH
Structural Steel Frame 5/3/2024 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Partial Approval JON MCHUGH
Structural Steel Frame 5/7/2024 Partial Approval JON MCHUGH
Deputy Steel/Welding 5/13/2024 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 9/4/2024 Not Ready for Inspection JON MCHUGH
Gas Test 9/4/2024 Partial Approval JON MCHUGH
Green Building Rough 9/4/2024 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 9/4/2024 Partial Approval JON MCHUGH
Rough-Elec/Plmb/HVAC 9/4/2024 Not Ready for Inspection JON MCHUGH
Sewer 9/4/2024 Approved JON MCHUGH
Underground Mechanical 9/4/2024 Partial Approval JON MCHUGH
Verify Sprinkler Sign Off 9/4/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 9/9/2024 Approved JON MCHUGH
HVAC-Rough 9/9/2024 Corrections Issued JON MCHUGH
PLUMBING-Rough 9/9/2024 Not Ready for Inspection JON MCHUGH
Deputy Drilled-In Anchors 9/17/2024 Conditional Approval JON MCHUGH
BUILDING-Rough-Frame 9/23/2024 Partial Approval JON MCHUGH
HVAC-Rough 9/23/2024 Approved JON MCHUGH
PLUMBING-Rough 9/23/2024 Approved JON MCHUGH
Shower Pan 9/23/2024 Approved JON MCHUGH
Insulation 10/3/2024 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 10/3/2024 Partial Approval JON MCHUGH
Insulation 10/15/2024 Approved JON MCHUGH
Interior/Exterior Lathing 10/15/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 10/24/2024 Approved JON MCHUGH
Drywall Nailing 10/24/2024 Approved JON MCHUGH
Green Building Rough 10/24/2024 Approved JON MCHUGH
Shower Pan 10/24/2024 Approved JON MCHUGH
Verify Sprinkler Sign Off 10/24/2024 Approved JON MCHUGH
Gas Test 2/11/2025 Approved MORRIS JACKSON
Final 7/3/2025 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 7/3/2025 Approved JON MCHUGH
Green Building Final 7/3/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved JON MCHUGH
Service/Power Release 7/3/2025 Approved JON MCHUGH
Smoke Detectors 7/3/2025 Approved JON MCHUGH
Final 9/10/2025 No Access for Inspection MORRIS JACKSON
Final 11/19/2025 Not Ready for Inspection JON MCHUGH
Final 2/4/2026 OK to Issue CofO JON MCHUGH
Special/Order Compliance 4/2/2026 Corrections Issued JON MCHUGH
Final 5/6/2026 OK to Issue CofO JON MCHUGH