6250 N LINDLEY AVE 91316
Certificate Information: 6250 N LINDLEY AVE 91316
- Application / Permit
- 21010-10000-03435
- Plan Check / Job No.
- B21LA12843
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | LAMAR DAVIS |
| Corrections Issued | 8/3/2021 | LAMAR DAVIS |
| Quality Review Completed | 8/11/2021 | KEN GILL |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Plan Check Approved | 7/27/2022 | LAMAR DAVIS |
| Issued | 12/8/2023 | APPLICANT |
| CofO in Progress | 2/4/2026 | JON MCHUGH |
| No Progress | 4/2/2026 | JON MCHUGH |
| CofO in Progress | 4/2/2026 | JON MCHUGH |
| CofO in Progress | 5/6/2026 | JON MCHUGH |
| CofO in Progress | 5/11/2026 | JOHN JANSON |
| Permit Finaled | 5/12/2026 | JOHN JANSON |
| CofO Issued | 5/12/2026 | JOHN JANSON |
| Permit Finaled | 5/12/2026 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 12/7/2021 | MIGUEL GAMBOA |
| Address approval | Cleared | 12/8/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | CARLOS AGUILERA |
| Permit | Cleared | 12/8/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/8/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/13/2021 | JOHN CONNEALLY |
| ZI | Cleared | 1/24/2022 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 4/26/2022 | NICK RAYGOZA |
| Trees in Parkway | Cleared | 6/17/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 7/27/2022 | LAMAR DAVIS |
| Miscellaneous | Cleared | 7/27/2022 | LAMAR DAVIS |
Contact Information
| Contractor | S A B D Investments Inc; Lic. No.: 1029441-B | 445 N FLORENCE STREET BURBANK, CA 91505 |
| Engineer | Casillas,, Rafael Ortega; Lic. No.: C68234 | 1937 S BRADSHAWE AVE MONTEREY PARK, CA 91754 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/6/2024 | Corrections Issued | JON MCHUGH |
| Underground Mechanical | 3/7/2024 | Corrections Issued | JEFFREY PARD |
| Underground Mechanical | 3/11/2024 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 3/13/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 3/19/2024 | Corrections Issued | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Approved | JON MCHUGH |
| Deputy Drilled-In Anchors | 5/2/2024 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Corrections Issued | JON MCHUGH |
| Structural Steel Frame | 5/3/2024 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | JON MCHUGH |
| Structural Steel Frame | 5/7/2024 | Partial Approval | JON MCHUGH |
| Deputy Steel/Welding | 5/13/2024 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 9/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Gas Test | 9/4/2024 | Partial Approval | JON MCHUGH |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 9/4/2024 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 9/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Sewer | 9/4/2024 | Approved | JON MCHUGH |
| Underground Mechanical | 9/4/2024 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 9/4/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 9/9/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 9/9/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 9/9/2024 | Not Ready for Inspection | JON MCHUGH |
| Deputy Drilled-In Anchors | 9/17/2024 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 9/23/2024 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 9/23/2024 | Approved | JON MCHUGH |
| PLUMBING-Rough | 9/23/2024 | Approved | JON MCHUGH |
| Shower Pan | 9/23/2024 | Approved | JON MCHUGH |
| Insulation | 10/3/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 10/3/2024 | Partial Approval | JON MCHUGH |
| Insulation | 10/15/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/15/2024 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 10/24/2024 | Approved | JON MCHUGH |
| Green Building Rough | 10/24/2024 | Approved | JON MCHUGH |
| Shower Pan | 10/24/2024 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 10/24/2024 | Approved | JON MCHUGH |
| Gas Test | 2/11/2025 | Approved | MORRIS JACKSON |
| Final | 7/3/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 7/3/2025 | Approved | JON MCHUGH |
| Green Building Final | 7/3/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 7/3/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 7/3/2025 | Approved | JON MCHUGH |
| Final | 9/10/2025 | No Access for Inspection | MORRIS JACKSON |
| Final | 11/19/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 2/4/2026 | OK to Issue CofO | JON MCHUGH |
| Special/Order Compliance | 4/2/2026 | Corrections Issued | JON MCHUGH |
| Final | 5/6/2026 | OK to Issue CofO | JON MCHUGH |