220 1/2-3/4 W 84TH PL 90003

Certificate Information: 220 1/2-3/4 W 84TH PL 90003

Application / Permit
21010-10000-03434
Plan Check / Job No.
B21LA12841
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ONE STORY ACCESSORY BUILDING (1200 SF) CONSISTING OF TWO ADUS PER GCS 65852.2 (E)(1)(C)
Permit Issued
Issued on 7/6/2022
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/14/2021 TSE MING HUANG
Corrections Issued 7/14/2021 TSE MING HUANG
Applicant returned to address corrections 7/15/2021 TSE MING HUANG
Building Plans Picked Up 7/21/2021 APPLICANT
Applicant returned to address corrections 5/20/2022 MINA HABILI
Plan Check Approved 7/6/2022 JOSEPH RAFOLS
Issued 7/6/2022 APPLICANT
CofO in Progress 1/31/2025 JOHN QUINTANILLA
Permit Finaled 2/11/2025 DEROLD HAUFF
CofO Issued 2/11/2025 DEROLD HAUFF
Permit Finaled 2/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/28/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/28/2021 RENZ SORIANO
Sewer availability Cleared 7/28/2021 RENZ SORIANO
Tenant Habitability Plan Cleared 9/8/2021 MICHAEL SOTO
Hydrant and Access approval Cleared 9/19/2021 ROBERT DUFF
Low Impact Development Cleared 11/1/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 11/15/2021 JEANETTE VONG
Construction near power lines Cleared 5/4/2022 RIDWAN HARDY
Construction within easement Cleared 5/19/2022 RIDWAN HARDY

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/24/2023 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 5/2/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/2/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 6/7/2023 Corrections Issued STUART CHAPMAN
Green Building Rough 6/7/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 6/7/2023 Approved STUART CHAPMAN
Wood Frame 6/7/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 6/12/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 6/15/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/3/2023 Approved MICHAEL LEWIS
Insulation 8/3/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 8/3/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Partial Inspection MICHAEL LEWIS
Sewer 8/7/2023 Approved MICHAEL LEWIS
Drywall Nailing 8/15/2023 Approved MICHAEL LEWIS
Green Building Rough 8/15/2023 Approved MICHAEL LEWIS
Insulation 8/15/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 8/28/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 3/15/2024 Corrections Issued MICHAEL LEWIS
Final 3/15/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 3/15/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 3/15/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 3/15/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 3/15/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 3/15/2024 Corrections Issued MICHAEL LEWIS
Final 8/21/2024 Partial Inspection MICHAEL LEWIS
Green Building Final 8/21/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/21/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 8/21/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 8/21/2024 Partial Inspection MICHAEL LEWIS
Final 8/23/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 8/23/2024 Not Required MICHAEL LEWIS
Smoke Detectors 8/23/2024 Approved MICHAEL LEWIS
Final 10/25/2024 Partial Inspection MICHAEL LEWIS
Final 11/25/2024 Partial Inspection MICHAEL LEWIS
Final 1/16/2025 No Access for Inspection JOHN QUINTANILLA
Final 1/23/2025 OK to Issue CofO JOHN QUINTANILLA