5212 S AVALON BLVD A-D 90011
Certificate Information: 5212 S AVALON BLVD A-D 90011
- Application / Permit
- 21010-10000-03424
- Plan Check / Job No.
- B21LA12825
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW THREE UNITS APARTMENT BUILDING WITH ATTACHED ADU PER LAMC 12.22 A.33 (c) AND (e) & ATTACHED THREE CAR GARAGE.
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Green Plans Picked Up | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 8/18/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/26/2021 | FARUK SEZER |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 1/6/2022 | APPLICANT |
| Applicant returned to address corrections | 1/5/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/11/2023 | SERGIO GUTIERREZ |
| Issued | 1/11/2023 | APPLICANT |
| CofO in Progress | 8/13/2025 | JAMES POWERS |
| CofO Issued | 8/18/2025 | ERNESTO CORRAL |
| Permit Finaled | 8/18/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Hold | Cleared | 8/9/2021 | JASON SHEETS |
| Hold | Cleared | 9/1/2021 | SERGIO GUTIERREZ |
| Address approval | Cleared | 10/18/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 11/8/2021 | AMAAN MALIK |
| Highway dedication | Cleared | 11/10/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | AMY SHUM |
| Historic Resource Verification | Cleared | 2/17/2022 | MAX LODER |
| "Q" conditions | Cleared | 5/4/2022 | RICHARD REASER |
| Frnt yard landscape/Water mgmt | Cleared | 5/9/2022 | RICHARD REASER |
| Redevelopment Project Area | Cleared | 5/11/2022 | SUSAN WONG |
| Low Impact Development | Cleared | 7/13/2022 | MARTIN FRAGOSO |
| Permit | Cleared | 7/19/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 9/30/2022 | MATTHEW CRAIG |
| Green Code | Cleared | 11/30/2022 | AARON COSTA |
| DAS Clearance | Cleared | 12/20/2022 | SERGIO GUTIERREZ |
Contact Information
| Contractor | La Casa Building Contractors; Lic. No.: 537961-B | 5425 S CENTRAL AVE LOS ANGELES, CA 90011 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/30/2023 | Partial Approval | NICK DANERI |
| Deputy Reinf. Concrete | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 6/12/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/12/2023 | Not Ready for Inspection | JAMES POWERS |
| Structural Steel Frame | 6/14/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/18/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/18/2023 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 8/30/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/30/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 8/30/2023 | Partial Approval | JAMES POWERS |
| Structural Steel Frame | 9/1/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 9/1/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 9/1/2023 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 11/14/2023 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 1/17/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 1/30/2024 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 1/30/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 2/12/2024 | Approved | JAMES POWERS |
| Drywall Nailing | 2/20/2024 | Approved | JAMES POWERS |
| Drywall Nailing | 3/4/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 4/30/2024 | Approved | JAMES POWERS |
| Final | 7/14/2025 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 7/14/2025 | Approved | JAMES POWERS |
| Green Building Final | 7/14/2025 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 7/14/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/14/2025 | Approved | JAMES POWERS |
| Wood Frame | 7/14/2025 | Approved | JAMES POWERS |
| Final | 8/12/2025 | OK to Issue CofO | JAMES POWERS |