1569 W GLEN AYLSA AVE 90041

Certificate Information: 1569 W GLEN AYLSA AVE 90041

Application / Permit
21010-10000-03417
Plan Check / Job No.
B21LA12809
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE AND LAMC 12.22 A33 (c)&(d). All work per Engineer Design.
Permit Issued
Issued on 8/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/20/2021 ZAW HAN
Corrections Issued 7/22/2021 ZAW HAN
Building Plans Picked Up 7/26/2021 APPLICANT
Applicant returned to address corrections 8/16/2022 GEORGE ALVAREZ
Plan Check Approved 8/25/2022 CRISTINA SALAZAR
Issued 8/29/2022 APPLICANT
CofO in Progress 4/11/2024 CRAIG VAUGHAN
Permit Finaled 4/12/2024 DEROLD HAUFF
CofO Issued 4/12/2024 DEROLD HAUFF
Permit Finaled 4/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 11/8/2021 AMAAN MALIK
Hydrant and Access approval Cleared 1/20/2022 KURT CORRAL
Low Impact Development Cleared 8/8/2022 TA ANH
Roof/Waste drainage to street Cleared 8/12/2022 AMAAN MALIK
GPI Written Notices Cleared 8/16/2022 ZAW HAN
Sewer availability Cleared 8/19/2022 AMAAN MALIK
Grading Pre-Inspection Cleared 8/25/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/6/2022 Partial Approval CRAIG VAUGHAN
Sewer 10/6/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 10/14/2022 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 10/17/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 12/28/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 12/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 12/28/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 12/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/28/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 1/10/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 1/10/2023 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 1/10/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 1/10/2023 Corrections Issued CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 1/10/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/13/2023 Approved CRAIG VAUGHAN
HVAC-Rough 1/13/2023 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 1/13/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 1/13/2023 Approved CRAIG VAUGHAN
Wood Frame 1/13/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 1/24/2023 Partial Approval CRAIG VAUGHAN
Underground Mechanical 1/24/2023 Approved CRAIG VAUGHAN
HVAC-Rough 2/24/2023 Approved OSVALDO PARAMO
Insulation 2/24/2023 Approved OSVALDO PARAMO
Shower Pan 2/24/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 3/21/2023 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 4/25/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 1/5/2024 Approved CRAIG VAUGHAN
Drywall Nailing 1/5/2024 Approved CRAIG VAUGHAN
Final 1/5/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 1/5/2024 Approved CRAIG VAUGHAN
Green Building Final 1/5/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV Not Required CRAIG VAUGHAN
Service/Power Release 1/5/2024 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 1/5/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 4/10/2024 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 4/10/2024 Approved CRAIG VAUGHAN
Smoke Detectors 4/10/2024 Approved CRAIG VAUGHAN