1547 W 85TH ST 90047

Certificate Information: 1547 W 85TH ST 90047

Application / Permit
21010-10000-03391
Plan Check / Job No.
B21LA12712
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE IN THE FRONT
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 12/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 DANIEL YIP
Corrections Issued 8/3/2021 DANIEL YIP
Quality Review Completed 8/12/2021 ALLEN MANALANSAN
Plan Check Approved 11/15/2021 DANIEL YIP
Issued 2/8/2022 APPLICANT
Building Plans Picked Up 2/10/2022 APPLICANT
CofO in Progress 11/17/2022 LILIANA PORTILLO
Permit Finaled 12/1/2022 DEROLD HAUFF
CofO Issued 12/1/2022 DEROLD HAUFF
Permit Finaled 12/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2021 WALLIE JONG
Highway dedication Cleared 8/26/2021 WALLIE JONG
Permit Cleared 8/26/2021 WALLIE JONG
Trees in Parkway Cleared 8/26/2021 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 8/30/2021 WALLIE JONG
Sewer availability Cleared 8/30/2021 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 8/31/2021 DENZEL HENDERSON
Hydrant and Access approval Cleared 10/29/2021 GILBERT URREA
Low Impact Development Cleared 11/4/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/9/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/23/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/23/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval LILIANA PORTILLO
Underground Mechanical 3/7/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Partial Approval ALEJANDRO DE ARTOLA
Insulation 3/8/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval LILIANA PORTILLO
Pre-Inspection 4/18/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Approved LILIANA PORTILLO
HVAC-Rough 8/2/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 8/2/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/3/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/3/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 8/3/2022 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/3/2022 Approved ALEJANDRO DE ARTOLA
Sewer 8/12/2022 Approved LILIANA PORTILLO
Underground Mechanical 8/12/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/16/2022 Approved ALEJANDRO DE ARTOLA
Green Building Rough 8/16/2022 Approved ALEJANDRO DE ARTOLA
Insulation 8/16/2022 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/16/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/23/2022 Approved LILIANA PORTILLO
Drywall Nailing 9/1/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/1/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/19/2022 Partial Approval LILIANA PORTILLO
Final 11/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 11/7/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 11/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 11/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 11/7/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/9/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 11/9/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/9/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/9/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/14/2022 Approved LILIANA PORTILLO
Final 11/14/2022 Conditional Approval LILIANA PORTILLO
Service/Power Release 11/14/2022 Approved LILIANA PORTILLO
Final 11/16/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 11/16/2022 Approved LILIANA PORTILLO