926 W 78TH ST 90044

Certificate Information: 926 W 78TH ST 90044

Application / Permit
21010-10000-03390
Plan Check / Job No.
B21LA12704
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 4-CAR GARAGE IN THE REAR
Permit Issued
Issued on 3/14/2022
Issuing Office
Current Status
CofO Issued on 11/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 DANIEL YIP
Corrections Issued 8/3/2021 DANIEL YIP
Quality Review Completed 8/12/2021 ALLEN MANALANSAN
Plan Check Approved 11/16/2021 DANIEL YIP
Issued 3/14/2022 APPLICANT
Building Plans Picked Up 3/15/2022 APPLICANT
CofO in Progress 10/5/2022 LILIANA PORTILLO
Permit Finaled 11/5/2022 DEROLD HAUFF
CofO Issued 11/5/2022 DEROLD HAUFF
Permit Finaled 11/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2021 CECILIO NAVARRO
Highway dedication Cleared 8/26/2021 CECILIO NAVARRO
Trees in Parkway Cleared 8/26/2021 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 8/27/2021 CECILIO NAVARRO
Low Impact Development Cleared 9/8/2021 MARTIN FRAGOSO
Hydrant and Access approval Cleared 10/29/2021 GILBERT URREA
Permit Cleared 11/2/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 11/2/2021 CELINA MORENO
Sewer availability Cleared 11/2/2021 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 11/4/2021 KENTON TRINH

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/21/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 4/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Approved LILIANA PORTILLO
HVAC-Rough 6/9/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 6/9/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/10/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 6/10/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 6/10/2022 Approved LILIANA PORTILLO
Special/Order Compliance 6/10/2022 Partial Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 6/10/2022 Approved LILIANA PORTILLO
Insulation 6/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 6/14/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/24/2022 Approved ALEJANDRO DE ARTOLA
Insulation 6/24/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/8/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/8/2022 Approved LILIANA PORTILLO
Sewer 7/29/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/29/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/29/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 9/28/2022 Approved LILIANA PORTILLO
Final 9/28/2022 OK to Issue CofO LILIANA PORTILLO
Green Building Final 9/28/2022 Approved LILIANA PORTILLO
HVAC-Final 9/28/2022 Approved LILIANA PORTILLO
PLUMBING-Final 9/28/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 9/28/2022 Approved LILIANA PORTILLO
Smoke Detectors 9/28/2022 Approved LILIANA PORTILLO
Service/Power Release 9/30/2022 Approved LILIANA PORTILLO