347-349 E 107TH ST 90003

Certificate Information: 347-349 E 107TH ST 90003

Application / Permit
21010-10000-03352
Plan Check / Job No.
B21LA12634
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT & ATTACHED 2-CAR GARAGE AT REAR
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 PRANITA SHAH
Corrections Issued 8/23/2021 PRANITA SHAH
Quality Review Completed 8/31/2021 MICHAEL PEREZ
Plan Check Approved 11/15/2021 PRANITA SHAH
Issued 3/16/2022 APPLICANT
Building Plans Picked Up 3/17/2022 APPLICANT
CofO in Progress 9/23/2022 ALIZAH MAYAGOITIA
Permit Finaled 10/15/2022 DEROLD HAUFF
CofO Issued 10/15/2022 DEROLD HAUFF
Permit Finaled 10/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2021 WALLIE JONG
Permit Cleared 9/10/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/21/2021 WALLIE JONG
Low Impact Development Cleared 9/21/2021 TA ANH
Roof/Waste drainage to street Cleared 9/23/2021 CELINA MORENO
Hydrant and Access approval Cleared 9/25/2021 ROBERT DUFF
Sewer availability Cleared 10/7/2021 WALLIE JONG
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/27/2022 Partial Approval JOHN KLARIN
Sewer 4/27/2022 Approved JOHN KLARIN
Wood Frame 4/27/2022 Partial Approval JOHN KLARIN
Insulation 5/2/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Corrections Issued JOHN KLARIN
HVAC-Rough 6/14/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 6/14/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 6/15/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 6/15/2022 Approved JOHN KLARIN
Green Building Rough 6/15/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 6/15/2022 Approved JOHN KLARIN
HVAC-Rough 6/27/2022 Approved ALIZAH MAYAGOITIA
Insulation 6/27/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 7/1/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 7/1/2022 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 7/13/2022 Approved JOHN KLARIN
ELECTRICAL-Final 8/30/2022 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Final 9/23/2022 Approved ALIZAH MAYAGOITIA
Final 9/23/2022 OK to Issue CofO ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/23/2022 Approved ALIZAH MAYAGOITIA
Gas Test 9/23/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 9/23/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 9/23/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/23/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 9/23/2022 Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/23/2022 Approved ALIZAH MAYAGOITIA
Service/Power Release 9/26/2022 Approved ALIZAH MAYAGOITIA