20511 W WELLS DR 91364

Certificate Information: 20511 W WELLS DR 91364

Application / Permit
21010-10000-03348
Plan Check / Job No.
B21LA12625
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 DANIEL YIP
Corrections Issued 8/9/2021 DANIEL YIP
Quality Review Completed 8/18/2021 JASON HEALEY
Applicant returned to address corrections 1/24/2022 DANIEL YIP
Plan Check Approved 3/11/2022 DANIEL YIP
Issued 3/23/2022 APPLICANT
Building Plans Picked Up 3/29/2022 APPLICANT
CofO in Progress 1/25/2024 MORRIS JACKSON
Permit Finaled 10/4/2025 MICHAEL PELHAM
CofO Issued 10/4/2025 MICHAEL PELHAM
Permit Finaled 10/4/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 8/19/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/19/2021 CARLOS AGUILERA
Permit Cleared 8/19/2021 CARLOS AGUILERA
Sewer availability Cleared 8/19/2021 CARLOS AGUILERA
Trees in Parkway Cleared 9/23/2021 JOEL HERNANDEZ
Hydrant and Access approval Cleared 10/20/2021 MATTHEW CRAIG
Low Impact Development Cleared 1/11/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 1/12/2022 CARLOS AGUILERA
GPI Written Notices Cleared 1/24/2022 DANIEL YIP
Grading Pre-Inspection Cleared 1/24/2022 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/20/2022 Partial Approval PETER FOLLING
Sewer 5/20/2022 Approved PETER FOLLING
Excavation/Setback/Form/Re-Bar 6/7/2022 Corrections Issued ROBERT GOLD
Footing/Foundation/Slab 6/7/2022 Corrections Issued ROBERT GOLD
Grounding or Bonding 6/7/2022 Not Ready for Inspection ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/13/2022 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 6/13/2022 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 6/16/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 7/22/2022 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 8/17/2022 Corrections Issued PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Not Ready for Inspection PETER FOLLING
Green Building Rough 8/17/2022 Not Ready for Inspection PETER FOLLING
Verify Sprinkler Sign Off 8/17/2022 Not Ready for Inspection PETER FOLLING
Wood Frame 8/17/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 8/25/2022 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Partial Approval PETER FOLLING
Green Building Rough 8/25/2022 Not Ready for Inspection PETER FOLLING
Verify Sprinkler Sign Off 8/25/2022 Not Ready for Inspection PETER FOLLING
Wood Frame 8/25/2022 Not Ready for Inspection PETER FOLLING
Deputy Wood Construction 1/10/2023 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 1/27/2023 Approved PETER FOLLING
ELECTRICAL-Rough 1/27/2023 Approved PETER FOLLING
Green Building Rough 1/27/2023 Approved PETER FOLLING
HVAC-Rough 1/27/2023 Approved PETER FOLLING
PLUMBING-Rough 1/27/2023 Approved PETER FOLLING
Verify Sprinkler Sign Off 1/27/2023 Approved PETER FOLLING
Insulation 2/14/2023 Approved PETER FOLLING
Shower Pan 2/14/2023 Not Ready for Inspection PETER FOLLING
Shower Pan 2/16/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 2/28/2023 Not Ready for Inspection PETER FOLLING
Drywall Nailing 3/8/2023 Approved PETER FOLLING
Interior/Exterior Lathing 4/5/2023 Approved PETER FOLLING
Final 8/16/2023 Corrections Issued PETER FOLLING
Green Building Final 8/16/2023 Not Ready for Inspection PETER FOLLING
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Not Ready PETER FOLLING
Service/Power Release 8/16/2023 Not Ready for Inspection PETER FOLLING
Smoke Detectors 8/16/2023 Not Ready for Inspection PETER FOLLING
Final 11/14/2023 Corrections Issued PETER FOLLING
Green Building Final 11/14/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 11/14/2023 SGSOV Not Ready PETER FOLLING
Service/Power Release 11/14/2023 Not Ready for Inspection PETER FOLLING
Smoke Detectors 11/14/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready JOHN KIDWELL
Final 11/28/2023 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Approved JOHN KIDWELL
Service/Power Release 11/28/2023 Approved JOHN KIDWELL
Final 1/24/2024 OK to Issue CofO MORRIS JACKSON