8731 1/2 S FIGUEROA ST 90003
Certificate Information: 8731 1/2 S FIGUEROA ST 90003
- Application / Permit
- 21010-10000-03341
- Plan Check / Job No.
- B21LA12613
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND STORY ADU WITH 3-CAR GARAGE BELOW PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | VIVIAN LAO |
| Corrections Issued | 8/23/2021 | VIVIAN LAO |
| Quality Review Completed | 9/1/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 6/28/2022 | APPLICANT |
| Applicant returned to address corrections | 9/8/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 10/3/2022 | VIVIAN LAO |
| Plan Check Approved | 1/23/2023 | VIVIAN LAO |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 8/15/2023 | MICHAEL LEWIS |
| CofO Issued | 8/28/2023 | DEROLD HAUFF |
| Permit Finaled | 8/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2021 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 10/15/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | AMAAN MALIK |
| Sewer availability | Cleared | 11/8/2021 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 1/25/2022 | RAFAEL FONTES |
| Hydrant and Access approval | Cleared | 3/1/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 4/1/2022 | TA ANH |
| Community Plan Implem. Overlay | Cleared | 10/11/2022 | MOHAMMAD HASAN |
| Roof/Waste drainage to street | Cleared | 10/28/2022 | AMAAN MALIK |
| Community Plan Implem. Overlay | Cleared | 1/7/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/7/2023 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 2/14/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/14/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/16/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 4/3/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 4/12/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/12/2023 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 4/12/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/14/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/14/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/17/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/17/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/18/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 4/18/2023 | Approved | LILIANA PORTILLO |
| Insulation | 4/18/2023 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 4/21/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 4/26/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/26/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/2/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/4/2023 | Conditional Approval | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/4/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/4/2023 | Corrections Issued | MICHAEL LEWIS |
| MERV13>=Final | 8/4/2023 | Corrections Issued | MICHAEL LEWIS |
| MERV13>=Rough | 8/4/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 8/4/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 8/4/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 8/4/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/9/2023 | Approved | MICHAEL LEWIS |
| Final | 8/9/2023 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Final | 8/9/2023 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/11/2023 | Approved | MICHAEL LEWIS |
| Final | 8/11/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 8/11/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 8/11/2023 | Approved | MICHAEL LEWIS |
| MERV13>=Final | 8/11/2023 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 8/11/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 8/16/2023 | Approved | MICHAEL LEWIS |