11654 N TRIPOLI AVE 91342

Certificate Information: 11654 N TRIPOLI AVE 91342

Application / Permit
21010-10000-03340
Plan Check / Job No.
B21LA12565
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 2/28/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 DANIEL YIP
Corrections Issued 8/19/2021 DANIEL YIP
Quality Review Completed 8/23/2021 JASON HEALEY
Building Plans Picked Up 8/31/2021 APPLICANT
Plan Check Approved 2/23/2023 DANIEL YIP
Issued 2/28/2023 APPLICANT
CofO in Progress 11/25/2025 MICHEL ABAJAN
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/3/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 10/4/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/8/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/8/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/14/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 3/31/2022 RUEL COLE
Low Impact Development Cleared 2/23/2023 ANTHONY VARGAS

Contact Information

Contractor Forty General Building Inc; Lic. No.: 1064226-B 6929 EL SELINDA AVE      BELL GARDENS, CA 90201

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/9/2023 Partial Approval MICHEL ABAJAN
Underground Mechanical 4/7/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/20/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 8/11/2023 Approved MICHEL ABAJAN
HVAC-Rough 8/11/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 8/11/2023 Approved MICHEL ABAJAN
Wood Frame 8/16/2023 Conditional Approval ROBERT GOLD
Insulation 8/21/2023 Not Ready for Inspection KEVIN BERBERYAN
Insulation 8/30/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/30/2023 Approved MICHEL ABAJAN
Drywall Nailing 9/11/2023 Approved MICHEL ABAJAN
Green Building Rough 9/11/2023 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 8/20/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/19/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/19/2025 Approved MICHEL ABAJAN
Final 5/19/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 5/19/2025 Approved MICHEL ABAJAN
HVAC-Final 5/19/2025 Approved MICHEL ABAJAN
PLUMBING-Final 5/19/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/19/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 5/19/2025 Approved MICHEL ABAJAN
Final 11/17/2025 Corrections Issued MICHEL ABAJAN
Final 11/24/2025 OK to Issue CofO MICHEL ABAJAN